INSP-Final Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Nick Phone #: ###-####
|
INSP-Final Inspection | 8/21/2019 | 8/22/2019 | 8/22/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need insulation and cover inspection for the piping in the storage closets.
Nick Phone #: ###-#### (change inspection to this afternoon, 8-22, per kristin dolan)
|
INSP-Final Inspection | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | FAIL |
Jim Page
|
|
|
Last inspection request was on 21MAY2019 for cover, notes indicate cover was not approved due too no tenting being installed, cover material has been installed and according to the last entry, cover was not approved.
Kristin Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
A tenting inspection was requested but no tenting has been installed.
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but piping can not be covered until a tenting inspection has passed.
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test witnessed with no visible loss on the guage. Todd Phone #: ###-####
|
INSP-Supply line flush | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed
Nick Phone #: ###-####
|