INSP-Final Inspection | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Corrections made. Permit can be finaled when alarm interconnections are verified.
|
INSP-Final Inspection | 5/3/2019 | 5/3/2019 | 5/3/2019 | P | CANC |
Troy Cobbley
|
|
|
Contact Leroy Anderson ###-#### prior to Fire Final Insp start please... We would like to schedule this for 2 O''Clock PM if possible please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | FAIL |
Troy Cobbley
|
|
|
Not all work has been completed. Such as relocating uprights along the new walls and adding/relocating heads around the ceiling fans and in storage rooms. Missing canopies in the mens showers.
Leroy is the contact ###-#### Phone #: ###-#### Inspection requested via web by Scott Carter II
|
INSP-Sprinkler Rough-in | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | CANC |
Troy Cobbley
|
|
|
Contact Tyler Loomis ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro was witnessed with no pressure loss.
Contact Tyler Loomis ###-#### 30 min prior to Hydro Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | CANC |
Troy Cobbley
|
|
|
The main drain valve failed. Contact Tyler Loomis ###-#### 30 min prior to insp start please, he would like to start at 2PM if at all possible.
Thanks Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2019 | 4/22/2019 | 4/22/2019 | A | FAIL |
Troy Cobbley
|
|
|
Called contact phone number but could not leave message since acount not set up. Went to job site did not find fitter and system has not been pumped up yet. No inspection performed.
Contact Tyler Loomis ###-#### 30 min prior to Hydro insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/19/2019 | 4/22/2019 | 4/19/2019 | P | CANC |
Troy Cobbley
|
|
|
Contact Tyler Loomis ###-#### 30 Min prior to Hydro Insp. start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/16/2019 | 4/19/2019 | 4/19/2019 | A | FAIL |
Jim Page
|
|
|
Flex heads have been used throught the office area of TI, city approved drawings show heads being hard piped, a resubmittal will be required to verify that the calcs will support flex head install.
Contact Tyler Loomis ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|