INSP-Final Inspection | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Please call Adam with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed at city pressure, no pressure loss observed.
Please call Adam with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Supply line flush | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Troy will coordinate with Suez. Troy Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Supply line flush | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Could not perform inspection due to time constraints. Please call troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 8/14/2019 | 8/14/2019 | 8/14/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
UG Cover Inspection. Troy N Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping is complete, piping between conditioned spaces approved for cover, piping in attic spaces that requires tenting/freeze protection is not approved for cover until tenting is installed, inspected and approved.
Cameron Phone #: ###-####
|