INSP-Final Inspection | 4/10/2020 | 4/13/2020 | 4/13/2020 | A | PASS |
Jim Page
|
|
|
Final inspection for underground supply is complete.
Kenny Caldwell is the contact. Have a good day (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2020 | 1/31/2020 | 1/31/2020 | A | PASS |
Troy Cobbley
|
|
|
Underground Hydro witnessed. Kenny Caldwell is the contact.Thanks for all you do. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush witnessed.
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | CANC |
Troy Cobbley
|
|
|
Not ready for hydro due to Suez needing an extended flush time because of water discoloration.
Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping and the remote FDC piping is ok for cover.
Bryan Collins is the for this underground RTC Inspection. He is hoping for and appointment around 11AM if possible. Thank you so much for your help. Have a great day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/1/2019 | 11/4/2019 | 11/4/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for area of rogh-in today.
Kenny Caldwell is the field contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in for piping and hangers passed for the north wing. See the city approved plans for location. Another rough to cover inspection will be required when the drops have been installed . I noted acouple of missing upright heads and possible blocked heads due to truss webbing. I went over the "three time rule" with fitter.
|
INSP-Sprinkler Rough-in | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Kenny Caldwell. Also wrong permit called in. We appreciate your help. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PART |
Jim Page
|
|
|
Inspection for IBR and remote FDC piping that passes under the footing complete (around 5 feet of pipe out from footing) , piping inspected approved for cover, remaining undergorund piping to be installed at a later date.
The contact is Jared. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|