Permit Information
Permit NumberFIR19-00386
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 7503 W NORTHVIEW ST
Project NameST MARKS CATHOLIC SCHOOL TI
Customer Number 
ePlanReviewYes
Description
SHILO WILL INSTALL A NEW SYSTEM IN AN EXISTING SCHOOL, STARTING WITH A 6" UG FROM THE PROPERTY LINE TO THE RISER ROOM. THIS WILL BE 1 WET SYSTEM IN A COMBUSTIBLE, 46,880 FT² BUILDING. ALL PIPE WILL BE HUNG EXPOSED UNDER THE CEILING. EXTENDED COVERAGE SIDEWALLS ON SPRIGS SHALL BE USED FOR MOST OF THE INSTALLATION. THE COMBUSTIBLE ATTIC SPACE SHALL BE FILLED WITH NON-COMBUSTIBLE INSULATION. THIS PLAN IS THE FIRST TWO PHASES OF A 4 PHASE PROJECT.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/13/20198/14/20198/14/2019APASS
DetailsJim Page
Previously noted items have been accepted, final fire sprinkler inspection complete for area of work.

This final has already been done, this is just the paper trail. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Conference8/6/20198/7/20198/7/2019ADONE
DetailsTroy Cobbley
Plans are in review status but I did note that several of the corridor sidewall heads appear to be blocked by adjacent walls and lockers.

George Jess is the contact. He would like this to take place before the hydro. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro8/6/20198/7/20198/7/2019APASS
DetailsTroy Cobbley
The overhead hydro for the wet system was witnessed with no pressure loss. No rough-in inspection performed due to plans being in review status. George Jess is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush7/23/20197/24/20197/24/2019PDONE
DetailsJim Page
Underground main line flush complete.

George Jess is the contact for this Underground Hydro and Flush. Stacey @ Suez said he would be able to help us at 1PM. We appreciate your help with this. Thank you Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro7/23/20197/24/20197/24/2019PDONE
DetailsJim Page
Hydrostatic test for undergound supply witnessed, no pressure loss observed.

George Jess is the contact for this Underground Hydro and Flush. Stacey @ Suez said he would be able to help us at 1PM. We appreciate your help with this. Thank you Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/2/20197/2/20197/2/2019PPASS
DetailsTroy Cobbley
Underground supply rough-in passed. Piping is ok for cover.

Bryan Collins is the contact. He would like this inspection as soon as possible today. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus