INSP-Final Inspection | 8/24/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact Andrew Larson ###-#### 30 Min prior to Final Insp start please, He request that this be later in the pm so Back Cert can be certified by Pacific Back Flow.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 8/22/2019 | 8/23/2019 | 8/23/2019 | P | FAIL |
Jim Page
|
|
|
Replace 2 heads that were painted. Head next to southeast exit is blocked by communication wires. Remove masking on sprinkler head.
Contact Andrew Larson - ###-#### 30 Min prior to Final Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items for rough in have been corrected, cover is approved.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2019 | 8/16/2019 | 8/16/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Contact Kieth Orahood 208-629--9953 30 min Prior to Hydro Insp start please. He''s requesting an Early PM insp if at all possible.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | FAIL |
Jim Page
|
|
|
Upright heads in meeting room C are still overspaced. No corrections were made to Quiet Room sidewalls or mech room blocked heads. Added head under stairs needs a hanger, almost 3 foot of unsupported pipe.
Contact Keith Orahood ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2019 | 8/5/2019 | 8/5/2019 | P | FAIL |
Jim Page
|
|
|
Upright head in Meeting Room C is overspaced, needs corrected. Correct head blockage in mechanical room, mech room has a duct over 48 inches that needs a head installed under, numerous heads are blocked by ductwork in mechanical room. Provide fire sprinkler protection under stairs per 8.15.3.2 of the 2016 NFPA13.
Verfiy that the sidewall heads in the "Quiet Room" meet the requirements of 8.7.4.1 of the 2016 NFPA 13 .
Contact Keith Orahood ###-#### 30 Min prior to RTC/Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | CANC |
Jim Page
|
|
|
Contact Keith Orahood ###-#### 30 Min prior to RTC/Hydro start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|