INSP-Final Inspection | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Call about 20 mins before // Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro test was witnessed with no visible pressure loss.
Matt Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints. Matt- approved plans are in the riser room in yellow manilla folder Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro witnessed with no pressure loss. Overhead rough-in passed. I noted that the big a** fans are being installed and may cause obstruction problems. I also noted a piece of equipment being constructed that incorporates some combustible concealed spaces that will need to be addressed as well.
Call 30 mins ahead- Matt Phone #: ###-####
|
INSP-Supply line flush | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush was witnessed. . Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Supply line flush | 10/8/2019 | 10/9/2019 | 10/9/2019 | P | CANC |
Troy Cobbley
|
|
|
This is going to be a supply line flush inspection. Please contact Heath Day prior to heading to job site at Phone #: ###-#### >> Inspection requested via web by Matt Barnard Inspection cancelled from web by: Matt Barnard
|
INSP-Sprinkler Rough-in | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough In Inspection is for the underground fire line passed. Piping can be covered. I noted that the remote PIV will need to have the tamper switch monitored by the fire alarm panel which will require wiring to be run. Please contact Matt Barnard one hour prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | PART |
Jim Page
|
|
|
Previously noted item for bury depth of IBR corrected, IBR is below 4foot 6 inches, IBR approved for cover, remaining undergorund to be installed at a later date.
Inspection of 6” In Building Riser. Please contact Matt Barnard one hour prior to showing up at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the IBR only. Piping is only at 3'-4 1/2" bury depth. 4'-6" is required to top of pipe. Need bury wire and plans/small documents.
Inspection of In Building Riser. Mega Lug to be installed and rodded back to 90 elbow once underground is installed. Contact Rick Fouts Phone #: ###-#### Inspection requested via web by Matt Barnard
|