INSP-Final Inspection | 11/20/2019 | 11/21/2019 | 11/21/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Cameron Phone #: ###-#### Inspection requested via web by Jeanine Halbesleben
|
INSP-Sprinkler Rough-in | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for east and west corridors and kitchen area complete, heads have been added in the combustible concealed spaces as discussed, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
John Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/21/2019 | 10/23/2019 | 10/23/2019 | A | PART |
Jim Page
|
|
|
Provide fire sprinklers above ceiling grid in areas where TGI's are installed due to more than 6 inches between ceiling grid and TGI's(kitchen area, east and west corridors), remaining areas approved for cover, TGI areas not approved for cover.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in attic space complete, attic piping is approved for cover. A follow up inspection will be required for cover of pendant head piping.
Cameran Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/19/2019 | 9/20/2019 | 9/20/2019 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 7/30/2019 | 8/5/2019 | 8/5/2019 | A | DONE |
Jim Page
|
|
|
Flush has been completed.
Flush with Suez at 10 am Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 8/2/2019 | 8/2/2019 | 8/2/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|