INSP-Final Inspection | 3/6/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Robert Chambers is the contact.Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauges.
Robert Chambers is the contact. Thanks! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2020 | 3/10/2020 | 3/10/2020 | A | CANC |
Jim Page
|
|
|
Robert Chambers is the contact. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/27/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, overhead fire sprinkler piping approved for cover.
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/24/2019 | 9/25/2019 | 9/25/2019 | A | PART |
Jim Page
|
|
|
Tenting inspection for units 1 and 2, starting from the southside complete, approved for cover, Remaining living units to be inspected at a later date.
Robert Chambers is the contact. This rough-in is for the 3rd floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for levels 1 and 2 witnessed, no pressure loss observed.
Robert Chambers is the contact. He would prefer this in the later afternoon/evening if possible. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 9/13/2019 | 9/13/2019 | 9/13/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection is complete, city approved drawings will need to show the additional head on level 3. Levels 1 and 2 are approved for cover, level 3 is not approved for cover until freeze protection is in place, inspected and approved for cover. Spray foam insulation is being used, the pocket between sheetrock and piping must be maintained, a letter of compatability needs to be submitted to Mark Stumbaugh, Fire Sprinkler Plan Reviewer, if spray foam is not compatable with CPVC piping then any and all piping that has spray foam on piping will be required to be replaced. As shown on city approved drawings, a minimum of R38 is required over the top of the piping.
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | FAIL |
Jim Page
|
|
|
Level 3 hydro complete with no loss at gauge, levels 1 and 2 both lost pressure.
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | CANC |
Jim Page
|
|
|
Rescheduled for 13SEPT2019 per conversation with point of contact, this request is cancelled.
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2019 | 9/10/2019 | 9/10/2019 | P | CANC |
Jim Page
|
|
|
Sprinkler design has been resubmitted for piping changes, hydro will not be completed until plans are re-issued and pipe changes are accepted without any other modification requirements, this request is cancelled.
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 9/9/2019 | 9/9/2019 | 9/9/2019 | A | DONE |
Jim Page
|
|
|
Letter of compatability needs to be submitted to the fire sprinkler plan reviewer in regards to the foam type insulation coming in contact with the CPVC sprinkler piping. Cover has not been approved for overhead fire sprinkler piping, any cover material installed that blocks the visual inspection for rough in will be required to be removed, as of this entry no cover is approved, fire conference is complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2019 | 9/10/2019 | 9/9/2019 | A | CANC |
Jim Page
|
|
|
Request was for a conference, this request is cancelled per conversation with point of contact.
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | CANC |
Jim Page
|
|
|
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | FAIL |
Jim Page
|
|
|
Installation does not match city approved drawings, most changes are on level 2 and remote area 4, no cover is approved.
Reashard Howard is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|