INSP-Final Inspection | 12/16/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the two locations where piping is ok for cover. I noted that the insulation that is falling from the deck will need repaired prior to anymore cover inspections. Phone #: ###-#### Inspection requested via web by Connie Danes
|