INSP-Conference | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | DONE |
Troy Cobbley
|
|
|
Per Tanner the mains need to be relocated on all floors. I will need as-builts/plan mods that show the actual installed location of all piping.
Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/29/2020 | 6/1/2020 | 6/1/2020 | A | CANC |
Troy Cobbley
|
|
|
screened // Tanner Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Troy Cobbley
|
|
|
The unnderground hydro test was witnessed. Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover. Kile Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line is ok for cover from the point of connection to the IBR. The IBR has not been installed yet and will require another inspection.
cover // Kyle Phone #: ###-####
|