INSP-Sprinkler Rough-in | 7/15/2020 | 7/16/2020 | 7/16/2020 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the soffits on all floors is ok for cover.
Mike Phone #: ###-#### **Rescheduled by JHB to 7/16 in AM after phone conversation with Mike**
|
INSP-Sprinkler Rough-in | 6/18/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Insulation for breezeway piping installed. All piping is ok for cover. Still need the head added to the 4th floor roof access room as discussed. Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | FAIL |
Troy Cobbley
|
|
|
The rough-in for the most part is good. But the 2" main piping is not shown for one feed and installed in the wrong size for the other feed. Plans need to show the heads in the closets on the 4th floor. Need insulation on breeze way piping, Need tenting repaired on the 4th and 3rd floors. It appears the standpipe may be in the wrong location. Need sprinkler coverage in the Roof Access/FACP room. Tanner *screened* Phone #: ###-####
|