INSP-Sprinkler Rough-in | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | PASS |
Troy Cobbley
|
|
|
UG cover inspection passed from point of connection to the building footing/wall. Piping is ok for cover. Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PART |
Jim Page
|
|
|
Inspection for 2 heads above rewquested hardlid was completed via text pictures, rough to cover inspection for the 2 heads on Level G stariwell are complete, area of work is approved for cover.
2 heads above hard lid ceiling. Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in/Hydro | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | PART |
Jim Page
|
|
|
Rough in inspection for sections SB and G is complete, a follow up inspection will be required before final for possible obstructions.
randy Phone #: ###-####
|
INSP-Sprinkler Rough-in | 3/24/2020 | 3/26/2020 | 3/26/2020 | A | CANC |
Jim Page
|
|
|
Cancel per Kerry Phone #: ###-#### >> Inspection requested via web by Lonnie Greenfield
|