INSP-Final Inspection | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in/Hydro | 7/28/2020 | 7/29/2020 | 7/29/2020 | A | PASS |
Troy Cobbley
|
|
|
Rough-in and overhead hydro witnessed. Piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Final Inspection | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Troy Cobbley
|
|
|
The combustible concealed space above the cooler has been filled with insulation. The area is ok for cover.
Look at insulation above cooler. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | DONE |
Troy Cobbley
|
|
|
The space above the cooler will need to meet one of the exceptions in NFPA 13 8.15 to delete coverage or sprinklers will need to be added.
Cooler room outside changed we had them fill with insulation need check it out before they cover. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 6/24/2020 | 6/25/2020 | 6/25/2020 | A | PASS |
Troy Cobbley
|
|
|
Piping above the hard lid in hall is ok for cover.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 6/24/2020 | 6/25/2020 | 6/24/2020 | P | CANC |
Troy Cobbley
|
|
|
Hard lids Phone #: ###-#### >> Inspection requested via web by Brian Carlisle Inspection cancelled from web by: Brian Carlisle
|