INSP-Final Inspection | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Troy Cobbley
|
|
|
A temp for fire alarm until the plans are submitted showing the added/changed module on the low air switch. All devices tested ok.
Contact is Davis. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | FAIL |
Troy Cobbley
|
|
|
Actually went to the project site twice today. The first trip the descripters from the device to the panel did not match. Low air came in as an alarm and rang the bell. Came back the second time and the monitoring company descriptors do not match. Will need to reschedule for tomorrow and a re-inspection fee has been applied. Contact is Davis. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | FAIL |
Troy Cobbley
|
|
|
The signal reports show a different designation for alarms than what is tested, old fire alarm devices need removed, the facp installed does not match the facp submitted, the basement plan has no stamp on it, the riser sheet was not provided. No devices tested.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|