INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Jim Page
|
|
|
Section of piping with sealant has been replaced, all tenting in place at time of inspection, cover is approved, cover sticker has been placed.
verify replacement of section of piping that had caulk on it. Also, tenting inspection. Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 3/19/2020 | 3/20/2020 | 3/20/2020 | P | PART |
Jim Page
|
|
|
Plans have been corrected. White sealant type compound has been applied to the electrical boxes, white sealant has come in contact with sprinkler piping section between level 1 and 2, need to have a letter submitted for compatability of sealant and CPVC or piping needs to be replaced. No tenting installed at time of inspection, cover is not approved.
Johnathon Phone #: ###-####
|
INSP-Sprinkler Rough-in | 3/16/2020 | 3/17/2020 | 3/17/2020 | P | FAIL |
Jim Page
|
|
|
Install does not match city approved drawings, plans were noted in a couple of areas but not all areas, re-submit will be required.
Jonathan Phone #: ###-####
|