INSP-Final Inspection | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, irrigation shut-down on flow switch activation has been witnessed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire srpinkler piping witnessed at city pressure, no pressure loss onserved at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Cover sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection is complete, no tenting installed at time of inspection, cover is not approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|