INSP-Final Inspection | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Jim Page
|
|
|
All piping is exposed, rough to cover not required, final fire sprinkler inspection for scope of work is complete.
Call Steve Johnson @###-#### for escort Phone #: ###-#### Inspection requested via web by Steve Johnson
|
INSP-Sprinkler Rough-in/Hydro | 3/26/2020 | 3/26/2020 | 3/26/2020 | A | DONE |
Jim Page
|
|
|
24 hour air test and hydrostatic test have been witnessed, no pressure loss was observed.
|