INSP-Final Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Tony Cetani is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | FAIL |
Troy Cobbley
|
|
|
Permit can be finaled when shell permit is finaled. Tony Cetani is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Alarm Testing | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | CANC |
Jim Page
|
|
|
Tony Cetani is the contact. Thanks! (: Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 6/29/2020 | 6/30/2020 | 6/30/2020 | P | CANC |
Troy Cobbley
|
|
|
The fire alarm was not ready and ceiling tile is missing.
The contact is Tony Cetani. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 6/29/2020 | 6/29/2020 | 6/29/2020 | P | CANC |
Jim Page
|
|
|
Tony Cetani is the contact. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 6/26/2020 | 6/29/2020 | 6/29/2020 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Tony Cetani is the contact. thanks so much for all your help! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for area of work is complete, approved for cover.
Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|