INSP-Sprinkler Rough-in/Hydro | 3/13/2001 | 3/14/2001 | 3/14/2001 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/13/2001 at 10:32:53. Contact: ###-####. see permit number FIR00-00123 for correct permit 3/14/2001 2:57:18 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2000 | 11/16/2000 | 11/16/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 11/16/2000 4:00:25 PM ///not complete 11/16/2000 4:00:53 PM
|
INSP-Sprinkler Rough-in | 9/18/2000 | 9/21/2000 | 9/21/2000 | A | PART |
Rick Jackson
|
|
|
###-#### tested the fire pump; 500 gpm pump tested at 150, 100 percent and churn; flushed dry standpipe at roof outlet; alarms not complete and will retest for alarms when they are complete 9/21/2000 9:13:56 AM
|
INSP-Sprinkler Rough-in | 9/14/2000 | 9/18/2000 | 9/18/2000 | A | PART |
Rick Jackson
|
|
|
todd ###-#### hydro okay for standpipes, FDC 9/18/2000 9:33:38 AM
|
INSP-Sprinkler Rough-in | 9/7/2000 | 9/12/2000 | 9/12/2000 | P | FAIL |
Rick Jackson
|
|
|
TODD- ###-#### R/I hydro test of 2,3,4,5,6 and attic areas pass; r/i revealed attic area not covered, 6th floor has major deviations from plans requiring resubmittal, head painted on 2nd janitor room, dry standpipe needs pitch to ensire drainage 9/13/2000 11:06:22 AM
|