GCB-Final | 8/21/2012 | 8/22/2012 | 8/22/2012 | A | PASS |
Mike Jordan
|
|
|
Jeremy @ ###-#### As early in the morning as possible please. Ok for perm occ. All issues have been resolved.
|
GCB-Final | 8/20/2012 | 8/21/2012 | 8/21/2012 | P | FAIL |
Mike Jordan
|
|
|
###-#### Jeremy PM Please. Rremove all thumbturns, provide single action door levers, install all missing handrails, move vertical grabbars in ADA stalls to comply with the 39 to 41 inches from wall, provide boots under sinks. Provide final letter from special inspection agency.
|
GCB-Framing | 8/2/2012 | 8/3/2012 | 8/3/2012 | A | PASS |
Mike Jordan
|
|
|
###-#### Drywall inspection. screw pattern for 1hr. fire wall ok.
|
GCB-Framing | 7/24/2012 | 7/25/2012 | 7/25/2012 | A | PASS |
Mike Jordan
|
|
|
###-####. Ok to cover 1hr. wall. Interior steel stud wall for hall to restrooms ok, restroom framing ok, framing at main entry and ticket booth ok.
|
GCB-Framing | 7/19/2012 | 7/20/2012 | 7/20/2012 | A | NR |
Tony Young
|
|
|
Jeremy @ ###-#### Call in advance - AM inspection,, not ready,, walk through conf. only,,, need trades signed off 1st,,, can cover some exterior walls if no trades
|
GCB-Energy | 6/28/2012 | 6/29/2012 | 6/29/2012 | A | PASS |
Jim Sly
|
|
|
Jeremy @ ###-#### Inspection requested for AM. Insulation inspection.
|
GCB-Framing | 6/25/2012 | 6/26/2012 | 6/26/2012 | A | PASS |
Dave Hannah
|
|
|
Jeremy @ ###-#### Call to coordinate ok to insulate dressing rooms and area above and around dressing rooms
|