GCB-Final | 7/12/2010 | 7/13/2010 | 7/13/2010 | A | PASS |
Mike Jordan
|
|
|
Scope: Final (Signature Only)Contact: Rich @ ###-####. Final ok.
|
GCB-Final | 7/7/2010 | 7/8/2010 | 7/8/2010 | A | NR |
Mike Jordan
|
|
|
Scope: FinalContact: Rich @ ###-####. Cards not signed, mech inspection failed. Needs to have cards signed to verify all finals are completed. Trades permits are not all attached and cannot verify finals on all trades. Spoke to leon with Garden City, they have been only looking at structural sign off. Noted to leon that card needs to have required final sign offs before issueing certificate of occupancies because trades permits are not all attached to building permits. Called contractor to have him reschedule all of his finals to have card signed. Also spoke to Bob Archibald about above issue.
|
GCB-Energy | 5/10/2010 | 5/10/2010 | 5/10/2010 | A | PASS |
Dave Hannah
|
|
|
|
GCB-Framing | 5/7/2010 | 5/10/2010 | 5/10/2010 | A | PASS |
Dave Hannah
|
|
|
Scope of inspection: Wall installationContact: Rich @ ###-####
|
GCB-Framing | 5/6/2010 | 5/7/2010 | 5/7/2010 | A | PASS |
Dave Hannah
|
|
|
Scope of inspection: Framing / Rough in Contact: Rich @ ###-#### ok to insulate
|
GCB-Energy | 5/6/2010 | 5/7/2010 | 5/7/2010 | A | PART |
Dave Hannah
|
|
|
Scope of inspection: EnergyContact: Rick @ ###-#### seal pakage ok
|
GCB-Footing | 4/6/2010 | 4/7/2010 | 4/7/2010 | A | PASS |
Dave Hannah
|
|
|
9:30 am requested
|