GCB-Final | 9/1/2010 | 9/2/2010 | 9/2/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FinalContact: Rick @ ###-####Call 30 mins in advance please
|
GCB-Ceiling Grid | 8/17/2010 | 8/18/2010 | 8/18/2010 | A | PART |
Dave Hannah
|
|
|
Scope: Ceiling GridContact: Rick @ ###-####Please call 30 mins in advance ok to cover ceiling in hallway
|
GCB-Energy | 8/3/2010 | 8/4/2010 | 8/4/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: Energy (This is for insulation related to the ceiling)Contact: Brent @ ###-####Call in advance roof insulation blowen in to fill spaces to under 6 inches and batted on rest of areas with no insulation
|
GCB-Energy | 7/9/2010 | 7/12/2010 | 7/12/2010 | A | CANC |
Dave Hannah
|
|
|
Scope: Applicant has requested a "cover" inspection. Energy seems like the next logical inspection, but please let me know if I need to change this task.Contact: Rick @ ###-####**Call 30 mins in advance**
|
GCB-Framing | 7/12/2010 | 7/12/2010 | 7/12/2010 | A | PASS |
Dave Hannah
|
|
|
ok to cover ceiling struc bracing for mec units ok
|
GCB-Framing | 6/29/2010 | 6/30/2010 | 6/30/2010 | A | PASS |
Mike Jordan
|
|
|
Scope of Inspection: FramingContact: Rick @ 8665058**Call 30 minutes in advance**. Interior steel stud framed walls for new classrooms.
|