GCB-Final | 1/19/2012 | 1/20/2012 | 1/20/2012 | A | PASS |
Dave Hannah
|
|
|
Darin @ ###-####Call 30 mins in advance for access
|
GCB-Fire Wall | 11/8/2011 | 11/9/2011 | 11/9/2011 | A | PASS |
Mike Jordan
|
|
|
Darin @ ###-####Call in advance. 5/8 type x at inside of canopy as per provided detail.
|
GCB-Energy | 10/26/2011 | 10/27/2011 | 10/27/2011 | A | PASS |
Mike Jordan
|
|
|
Darin @ ###-####Vapor Barrier. 2 layers of 15 lb. paper ok. at areas A, B and C.
|
GCB-Fire Wall | 10/17/2011 | 10/18/2011 | 10/18/2011 | A | PASS |
Dave Hannah
|
|
|
Darin @ ###-#### sheet rock in soffits ok
|
GCB-Framing | 10/17/2011 | 10/18/2011 | 10/18/2011 | A | PASS |
Dave Hannah
|
|
|
Darin @ ###-####
|
GCB-Energy | 10/6/2011 | 10/7/2011 | 10/10/2011 | A | DONE |
Dave Hannah
|
|
|
Darin @ ###-####
|
GCB-Energy | 10/6/2011 | 10/7/2011 | 10/7/2011 | A | PASS |
Mike Jordan
|
|
|
Darin @ ###-####. 2 layers of 15lb. paper ok.
|
GCB-Framing | 10/4/2011 | 10/5/2011 | 10/5/2011 | A | PASS |
Mike Jordan
|
|
|
Darin @ ###-####. Framing area A ok.
|
GCB-Energy | 9/27/2011 | 9/28/2011 | 9/28/2011 | A | PASS |
Mike Jordan
|
|
|
Aaron Goff ###-####--Inspection is for a vapor barrier prior to stucco. AM please. Areas D and E. 2 layers of 15 lb. paper installed.
|
GCB-Framing | 9/26/2011 | 9/27/2011 | 9/27/2011 | A | PASS |
Dave Hannah
|
|
|
Darren@###-####
|
GCB-Framing | 9/21/2011 | 9/22/2011 | 9/22/2011 | A | PART |
Dave Hannah
|
|
|
Darin @ ###-####
|
GCB-Framing | 9/15/2011 | 9/16/2011 | 9/16/2011 | A | PASS |
Dave Hannah
|
|
|
Daron @ ###-####
|
GCB-Stem wall | 9/13/2011 | 9/14/2011 | 9/14/2011 | A | PASS |
Dave Hannah
|
|
|
Daron @ ###-####call in advance
|
GCB-Footing | 9/9/2011 | 9/12/2011 | 9/12/2011 | A | PART |
Mike Jordan
|
|
|
Darin @ ###-####Pouring around 8 a.m.. Cocnrete already placed. Special inspector was on site.
|
GCB-Framing | 9/6/2011 | 9/7/2011 | 9/7/2011 | A | PART |
Dave Hannah
|
|
|
###-####Call in advance ok to cover second section of awning
|
GCB-Framing | 9/1/2011 | 9/2/2011 | 9/2/2011 | A | PART |
Mike Jordan
|
|
|
Darin @ ###-####. Steel stud framing for new storefronts at area E and portion of area D. Aslo spoke with plan review regarding section IBC section 706.5.2 (horizontal projecting elements) for fire walls. Need to have fire walls located on plans and provide details for 1 hr. fire rated resistance construction were applicable.
|
GCB-Fndatn/slab ins/fld vent | 8/22/2011 | 8/23/2011 | 8/23/2011 | A | PART |
Mike Jordan
|
|
|
Darin @ ###-####Call in advance. Work in progress on column stemwalls in area s B and C. WIll have special inspection.
|
GCB-Footing | 8/17/2011 | 8/18/2011 | 8/18/2011 | A | PART |
Dave Hannah
|
|
|
###-####Pouring at 11 amCall in advance first set of column pads ok spec will also inspect and test concrete
|