GCB-Final | 3/16/2012 | 3/19/2012 | 3/19/2012 | A | PASS |
Mike Jordan
|
|
|
John @ ###-#### Call for access. All issues resolved. Structural final ok. No card to sign. Could not verify other trades final.
|
GCB-Final | 3/13/2012 | 3/14/2012 | 3/14/2012 | A | FAIL |
Mike Jordan
|
|
|
John @ ###-####Call for access. Provide the required energy cert. and post. provide blower door test results and post or the third party check list. Correction notice posted.
|
GCB-Energy | 11/17/2011 | 11/18/2011 | 11/18/2011 | A | PASS |
Mike Jordan
|
|
|
Steve @ ###-####Call in advance
|
GCB-Final | 11/2/2011 | 11/3/2011 | 11/3/2011 | A | PASS |
Mike Jordan
|
|
|
Steve @ ###-####. Check for fireblocking on energy code inspection at fireplace. ok to insulate.
|
GCB-Framing | 9/1/2011 | 9/2/2011 | 9/2/2011 | A | CANC |
Mike Jordan
|
|
|
Shane @ ###-####PM Inspection.. Drove out to jobsite, no rough ins are completed. Called shane with colony himes, he noted that he did not need the inspection and to cancel. Charging time due to driving out to jobsite.
|
GCB-Fndatn/slab ins/fld vent | 8/16/2011 | 8/16/2011 | 8/16/2011 | A | PASS |
Dave Hannah
|
|
|
dane - ###-####
|
GCB-Footing | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | PASS |
Tom Arcoraci
|
|
|
FootingsRyan @ ###-####Call in Advance - PM Inspection
|
GCB-Footing | 8/8/2011 | 8/8/2011 | 8/8/2011 | P | CANC |
Mike Jordan
|
|
|
Job has been shut down as per conversation with Ryan.
|
GCB-Footing | 8/5/2011 | 8/8/2011 | 8/8/2011 | A | CANC |
Mike Jordan
|
|
|
FootingsRyan @ ###-####Call in advance - PM Inspection. Moved to pm.
|