Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberGCB11-00069
StatusFinaled
Name HANSEN-RICE INC
Site Address 203 E 37TH ST
Project NameBLD2011-00069
Customer Number 
ePlanReviewNo
Description
West Tech Boiler Works - ***2/2/12 PLAN MODIFICATION TO INCLUDE: REMODEL THE EXSTING OFFICE SPACES PER PLANS; REPLACE THE EXISTING OFFICE 'C' SLAB FLOOR WITH NEW; REMOVE AND REPLACE THE DOORS ON OFFICE 'D' AND 'C'; UPDATE LIGHT SWITCHING IN THE OFFICES; AND UPDATE INSULATION IN THE EXISTING OFFICE AREA. ALL WORK PER THE APPROVED PLANS AND ALL REVIEWING AGENCIES APPROVALS. SRZ***12/28/2011 PLAN MODIFICATION TO INCLUDE: COMPLETELY REMOVE EXISTING SOUTH WALL, EXISTING WEST WALL AND ROOF STRUCTURE DUE TO INSUFFICIENT EXISTING CONDITIONS IDENTIFIED BY INSPECTION; BUILD NEW STUD FRAMED BEARING WALLS, NEW STEMWALL FOOTINGS AND REBAR; CONSTRUCT NEW ROOF SYSTEM; PROVIDE NEW THICKENED SLAB EXTENDING UNDER EXISTING SLAB AT THE NEW POINT LOADED LOCATIONS AT THE INTERIOR BEARING WALL; REMOVE EXISTING PLUMBING FIXTURES AND REPLACE W/ NEW PER PLANS; AND ALL OTHER WORK PER THE APPROVED PLANS AND THE SRUCTURAL INSPECTORS FINAL APPROVAL. - SRZ** To construct a 499 square foot, one story, addition on to an existing 2,885 square foot existing commercial building per plans. Work also to include: remove existing window in the south wall and infill opening; provide new 2-hour rated wall assembly to south wall along the entire wall line; install a new Hi-Lo accessible drinking fountain; All work per the approved plans, engineering, attached plan review report, and all other reviewing agencies approvals. This building is not fire sprinklered. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final3/28/20123/29/20123/29/2012APASS
DetailsMike Jordan
Jerry @ ###-####. All issues resolved. Structural final only ok.
GCB-Final3/27/20123/28/20123/28/2012PFAIL
DetailsMike Jordan
Jerry @ ###-####
PM Inspection. Remove thumb turn from main entry door, provide sticker over main door "Yhis door to remain unlocked during bussiness hours" provide fire extinguishers, provide ada bathroom sign and post at required location.
GCB-Ceiling Grid3/15/20123/16/20123/16/2012ADONE
DetailsDave Hannah
Jerry @ ###-####
GCB-Energy3/12/20123/13/20123/13/2012APASS
DetailsMike Jordan
Jerry @ ###-####. OK to sheet rock.
GCB-Framing3/12/20123/12/20123/12/2012PPASS
DetailsMike Jordan
Jerry Phone #: ###-####. Airseal and fireblock completed. Ok to insulate.
GCB-Framing3/8/20123/9/20123/9/2012APART
DetailsMike Jordan
Jerry @ ###-####. Framing ok. Needs to complte sirseal and fire stop penetrations through top plates and at ceiling level along existing building.
GCB-Masonry2/21/20122/22/20122/22/2012APART
DetailsDave Hannah
Jerry @ ###-####Rebar crew is toping out last lift
GCB-Masonry2/17/20122/17/20122/17/2012PPASS
DetailsTom Arcoraci
GCB-Masonry2/16/20122/17/20122/17/2012ACANC
DetailsTom Arcoraci
Jerry @ ###-####(Rebar Inspection)
GCB-Shearwall2/14/20122/15/20122/15/2012APASS
DetailsMike Jordan
Jerry @ ###-####. Exterior shear nail ok. Reviewed and inspected truss repair from truss enginneer for roof trusses that have benn installed upside down. Inspected the 32/16 span rated osb on both sides with required nailing. ok to cover exterior sheathing only.
GCB-Framing2/3/20122/6/20122/6/2012AFAIL
DetailsMike Jordan
Jerry @ ###-####. Nails are over driven. Needs to renail. Also need RFI from engineer for repair on roof trusses that have been installed upside down.
GCB-Fndatn/slab ins/fld vent1/20/20121/23/20121/23/2012APASS
DetailsDave Hannah
Jerry @ ###-####
GCB-Footing1/19/20121/20/20121/20/2012APASS
DetailsDave Hannah
Jerry @ ###-####3 PM Inspection
GCB-Footing12/14/201112/15/201112/15/2011APASS
DetailsMike Jordan
Jerry @ ###-####11 a.m. inspection. Footing ok. Needs to have architect and engineer re-evaluate existing footing and foundation system.