GCB-Final | 4/5/2012 | 4/6/2012 | 4/6/2012 | P | PASS |
Mike Jordan
|
|
|
Jeremy @ ###-#### PM Inspection. Structural final ok.
|
GCB-Final | 4/4/2012 | 4/4/2012 | 4/4/2012 | A | FAIL |
Dave Hannah
|
|
|
Jeremy ###-#### needs to fix ada rest room and add sign also need landing for back door
|
GCB-Courtesy | 3/7/2012 | 3/8/2012 | 3/8/2012 | A | PASS |
Mike Jordan
|
|
|
Justin @ ###-####Contractor did not specify inspection type. Interior steel stud framed walls ok.
|
GCB-Framing | 2/22/2012 | 2/23/2012 | 2/24/2012 | A | PART |
Dave Hannah
|
|
|
Justin @ ###-####8 AM Inspection storage space walls ok to cover
|
GCB-Framing | 2/9/2012 | 2/10/2012 | 2/10/2012 | A | PASS |
Dave Hannah
|
|
|
Justin @ ###-####Call to confirmPre-Fab Structure Assembly
|
GCB-Fndatn/slab ins/fld vent | 1/10/2012 | 1/11/2012 | 1/11/2012 | A | PASS |
Mike Jordan
|
|
|
Jeremy @ ###-####. INspected welded wire mesh and vapor barrier for interior slab on grade.
|
GCB-Stem wall | 12/28/2011 | 12/29/2011 | 12/30/2011 | A | CANC |
Dave Hannah
|
|
|
contact Ed ###-####PM inspection
|
GCB-Fndatn/slab ins/fld vent | 12/29/2011 | 12/30/2011 | 12/30/2011 | A | PASS |
Dave Hannah
|
|
|
Dane @ ###-####AM Inspection Preferred
|
GCB-Footing | 12/23/2011 | 12/27/2011 | 12/27/2011 | A | PASS |
Dave Hannah
|
|
|
###-####
|
GCB-Footing | 12/22/2011 | 12/23/2011 | 12/23/2011 | A | CANC |
Dave Hannah
|
|
|
###-####
|