Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberGCB12-00009
StatusFinaled
Name Dave Evans Construcion
Site Address 6843 N STRAWBERRY GLENN RD
Project NameBLD2012-00004
Customer Number 
ePlanReviewNo
Description
Oliver Finley Academy- ***7-12-12 PLAN MODIFICATION TO INCLUDE: ADD NEW GUARDRAIL AND HANDRAILS IN THE COMMONS ROOM; ADD A NEW EXTERIOR WALL WINDOW IN THE EMPLOYEE LOUNGE ROOM 131; ADD A NEW WINDOW IN THE CLASSROOM 202; REMOVE INTERIOR WALLS AND DOORS DIVIDING THE COS. DISPENSARY, NAIL DISP. AND EST. DISP. ROOMS TO MAKE ALL ONE ROOM; AND MODIFY THE INTERIOR WALL BETWEEN R.R. 122 AND BODY WAX ROOM 121. SRZ*** To build-out for the first time two new tenant spaces (4,968 sq.ft. Annex space / 15,932 sq.ft. Main space) in an existing vacant shell spaces to be used as a beauty college per approved plans. Work to include: construction of new interior non-bearing walls to create: a fully accessible restrooms, classrooms, offices, waiting areas, laundry room, commons room, nail clinic, and associated instructional areas; installation of a suspended ceiling grid system installed per CISCA guidelines; related interior finishes in compliance with chapter 8 of the 2009 IBC; lighting, mechanical supply/exhaust systems, and plumbing fixtures. All work shall comply with the approved drawings, the plan review report, and all applicable codes. Energy code compliance for the envelope was part of the SHELL permit. Sealing & insulation of ductwork, mechanical and lighting compliance are a part of this permit. A new Certificate of Occupancy with the new occupant load total is to be issued when completed and approved. "This building is fully Fire Sprinklered. A portion of this building has an approved Fire Alarm system. Any alterations or
modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department." **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final8/31/20129/4/20129/4/2012APASS
DetailsMike Jordan
Dave @ ###-####. Structural final ok.
GCB-Ceiling Grid8/21/20128/22/20128/22/2012PPASS
DetailsMike Jordan
Dave @ ###-####
PM inspection requested. Remainder of ceiling grid (cloud) ok.
GCB-Ceiling Grid8/16/20128/16/20128/16/2012PPART
DetailsDave Hannah
Dave @###-####
Grid cover inspection
PM inspection for today requested. ok to cover all but the clouds crew still working on them
GCB-Ceiling Grid8/1/20128/2/20128/2/2012APASS
DetailsTom Arcoraci
Dave @ ###-####
Annex Side (E) of Project east side ok
GCB-Energy6/7/20126/8/20126/8/2012APASS
DetailsMike Jordan
Dave @ ###-####
Call in advance 30 mins. Plan mod and engineering will be sent to Sam Z. Insulation under stages installed and is ok.
GCB-Framing5/25/20125/29/20125/29/2012APART
DetailsJim Sly
Dave @ ###-####
OK with framing except.....Talked to Dave about some walls removed in rooms 137, 138 and 139.........and door filled in (same area). Architect to contact Sam Z. at plan check To verify if re-submittal needed for approval. Engineer to provide paperwork for wire supports at interior soffit .....Front entry to the South. OK to start insulating.
GCB-Courtesy5/8/20125/9/20125/9/2012PDONE
DetailsMike Jordan
Dave @ ###-####
Call 30 mins in advance - PM Inspection. Went over fire barrier wall isuues with contracotr and architect.