GCB-Final | 8/14/2012 | 8/14/2012 | 8/14/2012 | P | PASS |
Dave Hannah
|
|
|
Steve @ ###-#### PM Inspection
|
GCB-Framing | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | PART |
Mike Jordan
|
|
|
Robert @ ###-#### AM inspection requested Framing for facade. Needs to provide the correct track splice at corners and justify condition of simpson holdowns. ok to cover.
|
GCB-Shearwall | 7/11/2012 | 7/12/2012 | 7/12/2012 | A | PASS |
Mike Jordan
|
|
|
Robert @ ###-####. Shear walls for new store front ok.
|
GCB-Ceiling Grid | 7/9/2012 | 7/10/2012 | 7/10/2012 | A | PASS |
Mike Jordan
|
|
|
Robert @ ###-####. Hardlids ok to cover.
|
GCB-Framing | 7/6/2012 | 7/9/2012 | 7/9/2012 | P | CANC |
Mike Jordan
|
|
|
Robert @ ###-#### PM Inspection
|
GCB-Framing | 7/3/2012 | 7/5/2012 | 7/5/2012 | A | PART |
Dave Hannah
|
|
|
Robert @ ###-#### ext front soffiot ok to one side
|
GCB-Footing | 6/27/2012 | 6/28/2012 | 6/28/2012 | P | FAIL |
Mike Jordan
|
|
|
Robert @ ###-#### PM Inspection. Footing for compactor pad, Verts exceed the 16" O.C. spacing as shown on RFI and needs to provide 3" of clearance from bottom of footing to bottom of rebar. Correction notice was issued. MTI will verify repairs prior to placement and note on report.
|
GCB-Energy | 6/18/2012 | 6/19/2012 | 6/19/2012 | A | PASS |
Dave Hannah
|
|
|
Robert @ ###-#### ok to cover ext walls
|
GCB-Framing | 6/14/2012 | 6/15/2012 | 6/15/2012 | P | PASS |
Dave Hannah
|
|
|
Robert @ ###-#### PM Inspection ok to cover int walls ok to insulate ext walls
|
GCB-Footing | 5/24/2012 | 5/24/2012 | 5/24/2012 | P | PASS |
Tom Arcoraci
|
|
|
pending spec insp by mti
|
GCB-Footing | 5/23/2012 | 5/24/2012 | 5/24/2012 | A | CANC |
Tom Arcoraci
|
|
|
ROBERT @ ###-#### changed to pm per rob
|
GCB-Masonry | 5/21/2012 | 5/22/2012 | 5/22/2012 | A | PASS |
Mike Jordan
|
|
|
Robert @ ###-#### Inspection requested for as close to 9 a.m. as possible. 0 to 4ft. elevation at storefront. Also verified special inspections.
|
GCB-Fndatn/slab ins/fld vent | 5/15/2012 | 5/16/2012 | 5/16/2012 | A | PART |
Dave Hannah
|
|
|
Rob @ ###-#### Call in advance to coordinate. Stemwall for canopy columns. Will have special inspection. Also noted to contractor that special inspection firm needs to be contracted by the owner or desighn professional as per IBC capter 17 sec1703.1.1 and sec1704.1. Will give general contractor until next inspection to have issue resolved.
|
GCB-Footing | 5/14/2012 | 5/15/2012 | 5/15/2012 | A | CANC |
Jim Sly
|
|
|
Robert @ ###-#### Late AM inspection requested.Late AM inspection requested.Call in advance Duplicate added in by mistake.......Approx 34 min for inspection. Jim Sly ###-####
|
GCB-Footing | 5/14/2012 | 5/15/2012 | 5/15/2012 | A | PASS |
Jim Sly
|
|
|
Robert @ ###-#### Late AM inspection requested. Call in advance Al lfootings OK .....Pending MTI special inspection, tests and approvals.
|