Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberGCB12-00130
StatusFinaled
Name ALC Architecture
Site Address 6650 N GLENWOOD
Project NameBLD2012-00130
Customer Number 
ePlanReviewNo
Description
D & B Supply - To renovate the facade at the front of this existing 38,552 square foot Mercantile building. Work to include: remove existing roofing and infill existing facade with framing and stucco wall covering; construct new stucco cornice; construct two new engineered rough sawn wood canopies with standing seam metal roofing; exterior lighting; exterior site improvements including new sidewalk, curb ramp, accessible signage and vehicular bollards; and electrical work. All work per the approved plans, engineering, and other reviewing agencies approvals. NOTE: This building is fully fire sprinklered. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department and will require a separate permit. The existing envelope is not being affected by this permit. A certificate of completion shall be issued when work is completed and a final inspection has occurred. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final11/7/201311/8/201311/8/2013APASS
DetailsMike Jordan
Robert ###-#### call first. Structural final only ok.
GCB-Framing9/4/20139/4/20139/4/2013PPASS
DetailsMike Jordan
Dave ###-####. North and south canopy framing and heavy timber ok.
GCB-Framing8/12/20138/13/20138/13/2013APASS
DetailsMike Jordan
Terry ###-####. Steel stud framing for new storefront, south half.
GCB-Framing8/12/20138/12/20138/12/2013PNH
DetailsJim Storey
Terry ###-#### no one on site no plans defrered to am 8/13
GCB-Framing6/21/20136/24/20136/24/2013APART
DetailsDave Hannah
Dave ###-#### Partial framing north half on to cover
GCB-Framing6/20/20136/21/20136/21/2013ACANC
DetailsMike Jordan
###-#### Partial framing. Per contractor, this inspection was schedule for monday in the am , not today. Noted to contractor to contact garden city to reschedule for monday in the am.
GCB-Framing6/13/20136/14/20136/18/2013APART
DetailsDave Hannah
Dan ###-#### Partial framing inspect for exterior cover ok to cover north section
GCB-Footing2/19/20132/20/20132/20/2013PPASS
DetailsTony Young
DAN ###-####,, pier footings on north side of enterance ok per new engineering
GCB-Footing2/15/20132/6/20132/15/2013ADONE
DetailsDave Hannah
DAVE ###-#### AS CLOSE TO 2PM AS POSSIBLE PLEASE; PLAN TO POUR AT 3PM
GCB-Footing2/6/20132/6/20132/7/2013PPART
DetailsDave Hannah
Dave @###-#### four column ftgs south end ok to place concrete.