GCB-Final | 6/6/2013 | 6/6/2013 | 6/6/2013 | P | PASS |
Dave Hannah
|
|
|
Dan Phone #: ###-####
|
GCB-Final | 6/4/2013 | 6/5/2013 | 6/5/2013 | P | FAIL |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Provide blower door test results and post or the 3rd party airseal inspection report. Provide the approved energy cert and post. Remove roof vent from 4ft. laydown parapet and repair. Correction notice posted.
|
GCB-Energy | 4/29/2013 | 4/29/2013 | 4/30/2013 | P | PASS |
Dave Hannah
|
|
|
Dan ###-####
|
GCB-Framing | 4/26/2013 | 4/26/2013 | 4/26/2013 | P | PASS |
Jim Sly
|
|
|
Dan @ ###-#### Please inform GC Staff if any re-inspection fees should be applied to this project
|
GCB-Framing | 4/25/2013 | 4/25/2013 | 4/25/2013 | P | PART |
Jim Sly
|
|
|
Dan @ ###-#### OK to insulate......Need post in Gar.......point load from beam above. Need small pc. of rock at 2hr wall overbuild Garage.
|
GCB-Framing | 4/24/2013 | 4/24/2013 | 4/24/2013 | A | DEFR |
Dave Hannah
|
|
|
Dan ###-####
|
GCB-Fire Wall | 4/24/2013 | 4/24/2013 | 4/24/2013 | A | DEFR |
Dave Hannah
|
|
|
Dan ###-####
|
GCB-Framing | 4/24/2013 | 4/24/2013 | 4/24/2013 | P | NR |
Mike Jordan
|
|
|
Dan Phone #: ###-####. no mech. ri inspection.
|
GCB-Fire Wall | 4/24/2013 | 4/24/2013 | 4/24/2013 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
GCB-Courtesy | 3/18/2013 | 3/19/2013 | 3/19/2013 | A | PART |
Tom Arcoraci
|
|
|
Dan French @ ###-#### 2 hour wall issues sent to plan review
|
GCB-Footing | 2/15/2013 | 2/14/2013 | 2/19/2013 | P | DONE |
Dave Hannah
|
|
|
Heron @ ###-#### PM Inspection
|
GCB-Footing | 2/15/2013 | 2/15/2013 | 2/15/2013 | P | PASS |
Jim Sly
|
|
|
Huron-Ready at 3:30 Phone #: ###-####
|
GCB-Footing | 2/14/2013 | 2/14/2013 | 2/14/2013 | P | CANC |
Jim Sly
|
|
|
Heron @ ###-#### Contr. Cancelled.
|