GCB-Final | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Jim Sly
|
|
|
Julio ###-####
|
GCB-Final | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | PART |
Jim Sly
|
|
|
Julio ###-#### OK for Temp Occ. OK for Perm Occ when all other agencies are approved for Perm Occ.
|
GCB-Final | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | PEND |
Jim Sly
|
|
|
Julio ###-#### Walk thru
|
GCB-Framing | 9/15/2014 | 9/15/2014 | 9/15/2014 | P | PASS |
Dave Hannah
|
|
|
Julio ###-#### canopy framing inspectino request
|
GCB-Ceiling Grid | 9/4/2014 | 9/5/2014 | 9/5/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### Select ceiling grid OK.
|
GCB-Framing | 8/14/2014 | 8/15/2014 | 8/15/2014 | A | PART |
Jim Sly
|
|
|
###-#### Julio Verified installation of Tenmat FF109X fire rated light covers above can lights. Product approved by Sam Zahorka plan check.
|
GCB-Framing | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | CANC |
Jim Sly
|
|
|
|
GCB-Framing | 7/21/2014 | 7/22/2014 | 7/22/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-####
|
GCB-Framing | 7/10/2014 | 7/11/2014 | 7/11/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### Completes all framing insp.
|
GCB-Framing | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### Conf.
|
GCB-Framing | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | PART |
Mike Jordan
|
|
|
Julio ###-####. Framing at northwest qudrant and front canopy. Needs to install roll blocking on trusses at interior bearing wall locations. also discussed plan for can lights in rated roof/ceiling assemblies.
|
GCB-Framing | 6/20/2014 | 6/23/2014 | 6/23/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### Rooms only......2hr wall to West exterior wall.
|
GCB-Framing | 6/17/2014 | 6/20/2014 | 6/20/2014 | A | CANC |
Mike Jordan
|
|
|
Julio ###-####. Inspection cancelled.
|
GCB-Framing | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | CANC |
Mike Jordan
|
|
|
Julio ###-####. Per phone call from julio, inscpection was cancelled.
|
GCB-Framing | 6/10/2014 | 6/12/2014 | 6/12/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### Framing insp ....far West wing OK C/N No openings within 4' 2hr wall, Non rated can lights in rated ceiling. Method to close 1/2" gap at top of walls with hat channel, provide fire/smoke dampers at make up air...Hood.
|
GCB-Framing | 6/6/2014 | 6/9/2014 | 6/9/2014 | P | PART |
Jim Sly
|
|
|
Julio ###-#### Select Areas.
|
GCB-Energy | 6/4/2014 | 6/6/2014 | 6/6/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### spoke with Jim Sly about this inspection Sect 1.....OK
|
GCB-Fire Wall | 6/4/2014 | 6/6/2014 | 6/6/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### spoke with Jim Sly about this inspection #2 2hr wall OK.
|
GCB-Framing | 6/4/2014 | 6/6/2014 | 6/6/2014 | A | PART |
Jim Sly
|
|
|
Julio Area 2.......OK
|
GCB-Energy | 6/4/2014 | 6/4/2014 | 6/4/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### 2hr wall to East end of bldg.
|
GCB-Assembly | 6/2/2014 | 6/4/2014 | 6/4/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### roof sheeting inspection requested Select roof nailing.
|
GCB-Fire Wall | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Jim Sly
|
|
|
Julio ###-#### Rooms only .........Framing and Firestopping OK far East wing......up to 2 hr wall
|
GCB-Fire Wall | 5/30/2014 | 6/2/2014 | 6/2/2014 | A | NR |
Jim Sly
|
|
|
Julio ###-#### for a firestop
|
GCB-Assembly | 5/29/2014 | 6/2/2014 | 6/2/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### roof and wall sheeting (?) inspection requested N and W walls OK Roof OK
|
GCB-Fire Wall | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | DONE |
Jim Sly
|
|
|
Julio ###-#### Conference on Firestopping.
|
GCB-Assembly | 5/28/2014 | 5/29/2014 | 5/29/2014 | A | PART |
Mike Jordan
|
|
|
FIRE STOPS OTHER JULIO ###-####. SWork in progress on firestopping at area 1. Double layer 5/8 type x being installed in concelled areas behind tub and pex is being firecaulked. Electrical not yet started. K2 to call for additional inspection whwn area 1 is completed.
|
GCB-Framing | 5/23/2014 | 5/27/2014 | 5/27/2014 | A | PART |
Jim Sly
|
|
|
Julio Framing OK 2 East wings..... Need firestopping and listings. Do not insulate.
|
GCB-Assembly | 5/21/2014 | 5/23/2014 | 5/23/2014 | A | PART |
Tony Young
|
|
|
Julio ###-#### roof sheet/structural inspection request roof nailing ok
|
GCB-Shearwall | 5/6/2014 | 5/7/2014 | 5/7/2014 | A | PASS |
Mike Jordan
|
|
|
Julio ###-####. Exterior shear walls, north east portion and courtyards 1 and 2.
|
GCB-Framing | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PART |
Tom Arcoraci
|
|
|
Julio ###-#### roof framing/roof sheathing inspection requeste wip ok
|
GCB-Assembly | 4/24/2014 | 4/25/2014 | 4/25/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### roof nailing inspection request Section N. of Courtyard #3.....OK Circled on plan sheet.
|
GCB-Assembly | 4/21/2014 | 4/22/2014 | 4/22/2014 | P | NR |
Jim Sly
|
|
|
Herb ###-#### roof nailing inspection request; partial No access.
|
GCB-Assembly | 4/15/2014 | 4/16/2014 | 4/17/2014 | A | PART |
Dave Hannah
|
|
|
Herb ###-#### roof nailing inspection ok to cover see area marked on plans
|
GCB-Assembly | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | NR |
Jim Sly
|
|
|
Roof nailing.
|
GCB-Assembly | 4/11/2014 | 4/14/2014 | 4/14/2014 | A | CANC |
Jim Sly
|
|
|
Herb ###-#### roof nailing inspection
|
GCB-Assembly | 4/7/2014 | 4/8/2014 | 4/8/2014 | A | PART |
Tony Young
|
|
|
Herb ###-#### roof nailing inspection request Grace Assitsted Living,, far east wing ok
|
GCB-Fndatn/slab ins/fld vent | 12/27/2013 | 12/30/2013 | 12/30/2013 | A | PASS |
Dave Hannah
|
|
|
Herb ###-#### Pour at 10:30 am
|
GCB-Footing | 12/23/2013 | 12/24/2013 | 12/26/2013 | A | PART |
Dave Hannah
|
|
|
Herb ###-#### pouring at 9:30 am forms up and horz rebar in ground was coverd so there is no frost ok to place concrete
|
GCB-Footing | 12/20/2013 | 12/20/2013 | 12/20/2013 | P | DEFR |
Mike Jordan
|
|
|
Herb ###-#### (1:30 pour). Pending special inspection.
|
GCB-Fndatn/slab ins/fld vent | 12/17/2013 | 12/18/2013 | 12/18/2013 | P | PART |
Mike Jordan
|
|
|
Herb ###-#### Foundation pour at 1:30. Spoke therb. concrete has been placed. special inspector on site.
|
GCB-Fndatn/slab ins/fld vent | 12/16/2013 | 12/17/2013 | 12/18/2013 | P | PART |
Jim Sly
|
|
|
Herb ###-#### pour at 1:30 special inspection provided Select walls at NE and SE sect. OK pend. Geotech special inspections, tests and approvals.
|
GCB-Fndatn/slab ins/fld vent | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Tom Arcoraci
|
|
|
Herb ###-#### pouring concrete at noon spec inspector on site
|
GCB-Fndatn/slab ins/fld vent | 12/6/2013 | 12/6/2013 | 12/6/2013 | P | PEND |
Tony Young
|
|
|
Herb ###-#### Pouring cement 12/9 at 9:00,, pending special inspection and cold weather provisions
|
GCB-Footing | 12/2/2013 | 12/2/2013 | 12/2/2013 | P | PASS |
Tom Arcoraci
|
|
|
Herb ###-#### He would like closest to noon as possible, call first please spec inspec on site
|
GCB-Footing | 11/21/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Tom Arcoraci
|
|
|
Herb ###-####
|
GCB-Fndatn/slab ins/fld vent | 11/19/2013 | 11/20/2013 | 11/20/2013 | A | PART |
Mike Jordan
|
|
|
Herb ###-#### Geotech inspecting rebar also for noon foundation pour. Work in progress, pending special inspection, stemwall exterior of building, south side.
|
GCB-Fndatn/slab ins/fld vent | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | PASS |
Mike Jordan
|
|
|
Herb ###-#### Rebar for foundation inspection. East stemwall ok.
|
GCB-Footing | 11/12/2013 | 11/12/2013 | 11/13/2013 | A | PASS |
Tom Arcoraci
|
|
|
Herb ###-#### (2:00 concrete pour) spec insp on site
|
GCB-Footing | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | PART |
Tony Young
|
|
|
Herb ###-####,, work in progress,, special inspector on site,, back (south footing)
|
GCB-Courtesy | 11/5/2013 | 11/6/2013 | 11/6/2013 | A | DONE |
Mike Jordan
|
|
|
Herb ###-#### Call prior. Went over concrete special inspection requirements with contractor.
|