Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberGCB12-00156
StatusFinaled
Name K2 CONSTRUCTION
Site Address 9995 W STATE ST
Project NameBLD2012-00156
Customer Number 
ePlanReviewNo
Description
Grace At State Street - **71/11/14 PLAN MODIFICATION TO INCLUDE: MECHANICAL CHANGES AS APPROVED BY MECHANICAL PLAN REVIEW. SRZ***11/26/13 PLAN MODIFICATIONS TO INCLUDE: REMOVED PATIOS AND EXTERIOR UNIT DOORS ON NORTH AND EAST SIDES; REMOVED NORTH-MOST CARPORT AT THE EAST SIDE LOCATION; REDUCED THE SIZE OF THE UNIT ENTRY DOORS DUE TO NO BED MOVEMENT AND LIMITED CARE LICENSING; REMOVED 2-HOUR FIRE WALL EXTENSIONS; MIRRORED UNIT 266; PLUMBING, MECHANICAL, ELECTRICAL MODIFICATIONS PER PLANS; AND ALLOTHER MODIFICATIONS PER ADDENDUM NO.2. SRZ*** Scope of work includes construction of a 70,679 sq. ft., single story, fully sprinklered, Type VA construction, divided by (6) 2-hour fire walls to create four buildings for allowable floor area compliance based on type of construction (13, 122 sq. ft. / 35,634 sq. ft. / 12,797 sq. ft. / 9,126 sq. ft.); with 85 supervised residential units (38 one bedroom units @ 576 sq. ft.; 40 Studio Units @ 416 sq. ft.; 1 Studio Unit @ 523; 4 two bedroom units @ 818 sq. ft.; and 2 two bedroom units @ 780 sq. ft.; use of 2-hour fire walls and (3) 1-hour smoke barrier walls create (6) smoke compartments; 1-hour smoke partitions to create a smoke resistant corridor system; a kitchen, dining and socializing area; laundry, mechanical and common use support areas. There are four interior courts (3,966 sq. ft. / 3,044 sq. ft. / 5,734 sq. ft. / 4,015 sq. ft.) that exit back through the facility; installation of electrical, mechanical, plumbing, sprinkler and alarm systems; and all associated site work and landscaping. All work per the approved plans, attached plan review comments, and conditions of all reviewing agencies for this project. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final9/18/20149/18/20149/18/2014PPASS
DetailsJim Sly
Julio ###-####
GCB-Final9/16/20149/17/20149/17/2014PPART
DetailsJim Sly
Julio ###-####
OK for Temp Occ. OK for Perm Occ when all other agencies are approved for Perm Occ.
GCB-Final9/16/20149/16/20149/16/2014PPEND
DetailsJim Sly
Julio ###-####
Walk thru
GCB-Framing9/15/20149/15/20149/15/2014PPASS
DetailsDave Hannah
Julio ###-#### canopy framing inspectino request
GCB-Ceiling Grid9/4/20149/5/20149/5/2014APART
DetailsJim Sly
Julio ###-####
Select ceiling grid OK.
GCB-Framing8/14/20148/15/20148/15/2014APART
DetailsJim Sly
###-#### Julio
Verified installation of Tenmat FF109X fire rated light covers above can lights. Product approved by Sam Zahorka plan check.
GCB-Framing7/31/20148/1/20148/1/2014ACANC
DetailsJim Sly
GCB-Framing7/21/20147/22/20147/22/2014APASS
DetailsJim Sly
Julio ###-####
GCB-Framing7/10/20147/11/20147/11/2014APASS
DetailsJim Sly
Julio ###-####
Completes all framing insp.
GCB-Framing7/7/20147/8/20147/8/2014APART
DetailsJim Sly
Julio ###-####
Conf.
GCB-Framing6/30/20147/1/20147/1/2014APART
DetailsMike Jordan
Julio ###-####. Framing at northwest qudrant and front canopy. Needs to install roll blocking on trusses at interior bearing wall locations. also discussed plan for can lights in rated roof/ceiling assemblies.
GCB-Framing6/20/20146/23/20146/23/2014APASS
DetailsJim Sly
Julio ###-####
Rooms only......2hr wall to West exterior wall.
GCB-Framing6/17/20146/20/20146/20/2014ACANC
DetailsMike Jordan
Julio ###-####. Inspection cancelled.
GCB-Framing6/16/20146/16/20146/16/2014PCANC
DetailsMike Jordan
Julio ###-####. Per phone call from julio, inscpection was cancelled.
GCB-Framing6/10/20146/12/20146/12/2014APART
DetailsJim Sly
Julio ###-####
Framing insp ....far West wing OK C/N No openings within 4' 2hr wall, Non rated can lights in rated ceiling. Method to close 1/2" gap at top of walls with hat channel, provide fire/smoke dampers at make up air...Hood.
GCB-Framing6/6/20146/9/20146/9/2014PPART
DetailsJim Sly
Julio ###-####
Select Areas.
GCB-Energy6/4/20146/6/20146/6/2014APART
DetailsJim Sly
Julio ###-#### spoke with Jim Sly about this inspection
Sect 1.....OK
GCB-Fire Wall6/4/20146/6/20146/6/2014APASS
DetailsJim Sly
Julio ###-#### spoke with Jim Sly about this inspection
#2 2hr wall OK.
GCB-Framing6/4/20146/6/20146/6/2014APART
DetailsJim Sly
Julio
Area 2.......OK
GCB-Energy6/4/20146/4/20146/4/2014APART
DetailsJim Sly
Julio ###-####
2hr wall to East end of bldg.
GCB-Assembly6/2/20146/4/20146/4/2014APART
DetailsJim Sly
Julio ###-#### roof sheeting inspection requested
Select roof nailing.
GCB-Fire Wall6/2/20146/2/20146/2/2014PPASS
DetailsJim Sly
Julio ###-####
Rooms only .........Framing and Firestopping OK far East wing......up to 2 hr wall
GCB-Fire Wall5/30/20146/2/20146/2/2014ANR
DetailsJim Sly
Julio ###-#### for a firestop
GCB-Assembly5/29/20146/2/20146/2/2014APASS
DetailsJim Sly
Julio ###-#### roof and wall sheeting (?) inspection requested
N and W walls OK Roof OK
GCB-Fire Wall5/29/20145/30/20145/30/2014ADONE
DetailsJim Sly
Julio ###-####
Conference on Firestopping.
GCB-Assembly5/28/20145/29/20145/29/2014APART
DetailsMike Jordan
FIRE STOPS OTHER JULIO ###-####. SWork in progress on firestopping at area 1. Double layer 5/8 type x being installed in concelled areas behind tub and pex is being firecaulked. Electrical not yet started. K2 to call for additional inspection whwn area 1 is completed.
GCB-Framing5/23/20145/27/20145/27/2014APART
DetailsJim Sly
Julio
Framing OK 2 East wings..... Need firestopping and listings. Do not insulate.
GCB-Assembly5/21/20145/23/20145/23/2014APART
DetailsTony Young
Julio ###-#### roof sheet/structural inspection request
roof nailing ok
GCB-Shearwall5/6/20145/7/20145/7/2014APASS
DetailsMike Jordan
Julio ###-####. Exterior shear walls, north east portion and courtyards 1 and 2.
GCB-Framing5/1/20145/2/20145/2/2014APART
DetailsTom Arcoraci
Julio ###-#### roof framing/roof sheathing inspection requeste wip ok
GCB-Assembly4/24/20144/25/20144/25/2014APART
DetailsJim Sly
Julio ###-#### roof nailing inspection request
Section N. of Courtyard #3.....OK Circled on plan sheet.
GCB-Assembly4/21/20144/22/20144/22/2014PNR
DetailsJim Sly
Herb ###-#### roof nailing inspection request; partial
No access.
GCB-Assembly4/15/20144/16/20144/17/2014APART
DetailsDave Hannah
Herb ###-#### roof nailing inspection ok to cover see area marked on plans
GCB-Assembly4/14/20144/14/20144/14/2014PNR
DetailsJim Sly
Roof nailing.
GCB-Assembly4/11/20144/14/20144/14/2014ACANC
DetailsJim Sly
Herb ###-#### roof nailing inspection
GCB-Assembly4/7/20144/8/20144/8/2014APART
DetailsTony Young
Herb ###-#### roof nailing inspection request Grace Assitsted Living,, far east wing ok
GCB-Fndatn/slab ins/fld vent12/27/201312/30/201312/30/2013APASS
DetailsDave Hannah
Herb ###-#### Pour at 10:30 am
GCB-Footing12/23/201312/24/201312/26/2013APART
DetailsDave Hannah
Herb ###-#### pouring at 9:30 am forms up and horz rebar in ground was coverd so there is no frost ok to place concrete
GCB-Footing12/20/201312/20/201312/20/2013PDEFR
DetailsMike Jordan
Herb ###-#### (1:30 pour). Pending special inspection.
GCB-Fndatn/slab ins/fld vent12/17/201312/18/201312/18/2013PPART
DetailsMike Jordan
Herb ###-#### Foundation pour at 1:30. Spoke therb. concrete has been placed. special inspector on site.
GCB-Fndatn/slab ins/fld vent12/16/201312/17/201312/18/2013PPART
DetailsJim Sly
Herb ###-#### pour at 1:30 special inspection provided
Select walls at NE and SE sect. OK pend. Geotech special inspections, tests and approvals.
GCB-Fndatn/slab ins/fld vent12/12/201312/13/201312/13/2013APART
DetailsTom Arcoraci
Herb ###-#### pouring concrete at noon spec inspector on site
GCB-Fndatn/slab ins/fld vent12/6/201312/6/201312/6/2013PPEND
DetailsTony Young
Herb ###-#### Pouring cement 12/9 at 9:00,, pending special inspection and cold weather provisions
GCB-Footing12/2/201312/2/201312/2/2013PPASS
DetailsTom Arcoraci
Herb ###-#### He would like closest to noon as possible, call first please spec inspec on site
GCB-Footing11/21/201311/22/201311/22/2013PPASS
DetailsTom Arcoraci
Herb ###-####
GCB-Fndatn/slab ins/fld vent11/19/201311/20/201311/20/2013APART
DetailsMike Jordan
Herb ###-#### Geotech inspecting rebar also for noon foundation pour. Work in progress, pending special inspection, stemwall exterior of building, south side.
GCB-Fndatn/slab ins/fld vent11/14/201311/15/201311/15/2013APASS
DetailsMike Jordan
Herb ###-#### Rebar for foundation inspection. East stemwall ok.
GCB-Footing11/12/201311/12/201311/13/2013APASS
DetailsTom Arcoraci
Herb ###-#### (2:00 concrete pour) spec insp on site
GCB-Footing11/7/201311/8/201311/8/2013APART
DetailsTony Young
Herb ###-####,, work in progress,, special inspector on site,, back (south footing)
GCB-Courtesy11/5/201311/6/201311/6/2013ADONE
DetailsMike Jordan
Herb ###-#### Call prior. Went over concrete special inspection requirements with contractor.