GCB-Final | 6/22/2015 | 6/23/2015 | 6/23/2015 | A | PASS |
Dave Hannah
|
|
|
Manny ###-####
|
GCB-Framing | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | PASS |
Dave Hannah
|
|
|
Mark ###-#### - requested 30min call ahead insulation also ok
|
GCB-Framing | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | FAIL |
Jim Sly
|
|
|
Mark ###-#### - requested 30min call ahead c/n complete rock ....4' each side 2hr wall.
|
GCB-Framing | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | PART |
Dave Hannah
|
|
|
Mark ###-#### ok to insulate party walls
|
GCB-Shearwall | 7/19/2013 | 7/19/2013 | 7/19/2013 | P | PASS |
Tom Arcoraci
|
|
|
Josh ###-#### call first
|
GCB-Framing | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | CANC |
Jim Sly
|
|
|
###-#### Josh All nailing for shear and 2hr. wall OK @ all concealed spaces at boxed pop outs.......Rear wall and Gar. fronts. Note:......Need retro fit HD's at Gar. front portal.
|
GCB-Fndatn/slab ins/fld vent | 5/6/2013 | 5/6/2013 | 5/7/2013 | P | PASS |
Jim Sly
|
|
|
Mana ###-####
|
GCB-Fndatn/slab ins/fld vent | 5/3/2013 | 5/3/2013 | 5/6/2013 | P | CANC |
Jim Sly
|
|
|
Mana ###-####
|
GCB-Footing | 4/30/2013 | 5/1/2013 | 5/1/2013 | A | PART |
Mike Jordan
|
|
|
MANA ###-#### Between 9-10. Needs to replace some form boards to meet min. footing depths.
|
GCB-Footing | 4/29/2013 | 4/29/2013 | 4/30/2013 | P | CANC |
Tony Young
|
|
|