Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberGCB13-00085
StatusFinaled
Name Nelson's RV
Site Address 5309 CHINDEN BLVD
Project NameBLD2013-00083
Customer Number 
ePlanReviewNo
Description
Nelson's R.V.'s - To construct a new 6,200 sq. ft., one story, pre-engineered metal building and related site improvements. Work to include: concrete footings, concrete foundations, concrete slab on grade floor, pre-engineered metal building, overhead doors, man doors, windows, and interior nonbearing walls. Two single user toilet rooms will also be constructed. All work per the approved plans, Engineering, and all other reviewing agencies approvals. Racking exceeding 8' in height is NOT approved under this permit. NOTE: This building is NOT fire sprinklered. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final3/19/20143/20/20143/20/2014APASS
DetailsJim Sly
Dante ###-####
GCB-Final3/18/20143/19/20143/19/2014ANR
DetailsJim Sly
Dante ###-####
GCB-Ceiling Grid2/24/20142/24/20142/25/2014PPASS
DetailsDave Hannah
Dante ###-####
GCB-Fire Wall2/5/20142/5/20142/5/2014PPASS
DetailsJim Sly
East wall and columns....OK.
GCB-Framing2/4/20142/5/20142/5/2014APASS
DetailsJim Sly
GCB-Fire Wall2/4/20142/5/20142/5/2014ACANC
DetailsJim Sly
Dante ###-####.
GCB-Framing2/3/20142/4/20142/4/2014ACANC
DetailsJim Sly
Dante ###-####
Re-sched.......
GCB-Fire Wall2/3/20142/4/20142/4/2014ACANC
DetailsJim Sly
Dante ###-#### Re-sched.....
GCB-Framing1/30/20141/31/20141/31/2014APART
DetailsJim Sly
Dante ###-####
C/N posted
GCB-Fire Wall1/17/20141/21/20141/21/2014PPART
DetailsJim Sly
Dante ###-####
Double layer rock on East wall complete. Next step....columns.
GCB-Fire Wall1/16/20141/17/20141/17/2014APART
DetailsJim Sly
dANTE ###-####
OK for 2nd layer of rock between column 5 and 6 counting from the North. OK to install 1st layer between columns 4 to 5 and 6 to 7. Contr. to Provide letter from Architect ........rock to terminate at insulation in lieu of going all the way to the metal roof deck as shown on appr. plan.
GCB-Shearwall1/14/20141/15/20141/15/2014APART
DetailsJim Sly
Looked at inside of 1hr rated East wall. 1st layer of rock OK starting from the North end ......up to the 4th column. OK to install 2nd layer to this area. OK to install 1st layer of rock on remainder of East wall. Per detai B&C l...Page A 7.4 Shows UL 263 no.x649 Paintable firestop for columns? and also shows wrapping columns with rock.......But has been X'd out. Contractor wants to mix and match ...paint and wrap on select columns. Architect to get approval from City of Boise for using both these methods.
GCB-Framing1/13/20141/13/20141/13/2014PPART
DetailsMike Jordan
Dante ###-####
GCB-Energy1/13/20141/13/20141/13/2014PPASS
DetailsMike Jordan
Dante ###-####
GCB-Fire Wall12/17/201312/18/201312/18/2013APART
DetailsMike Jordan
Dante ###-####. East firewall, exterior 5/8 rock ok to cover.
GCB-Stem wall11/4/201311/5/201311/5/2013APART
DetailsMike Jordan
Dante ###-####. Special inspection.
GCB-Footing10/28/201310/28/201310/28/2013PPART
DetailsTony Young
Dante ###-#### Call first--needs inspected TODAY for concrete pour tomorrow.,, pending special inspection
GCB-Ceiling Grid9/20/20139/20/20139/23/2013PCANC
DetailsDave Hannah
Bill ###-####