Permit Information
Permit NumberGCB13-00113
StatusFinaled
Name CUSTOM STEEL STRUCTURES
Site Address 215 W 41ST ST
Project NameBLD2013-00111
Customer Number 
ePlanReviewNo
Description
(EBERLE STORAGE FACILITY) This permit is to construct a new 19,800 square foot storage / office building. Work is to include: construction of new foundation, all new site development work, construction of a metal building shell, all new envelope insulation for the entire building, construction of interior non-bearing walls to create 1,307 square foot office area and a 2,168 square foot private storage area, new mechanical, new electrical, new plumbing, and interior finishes. This building will be fully Fire Sprinklered with an approved Fire Alarm system per NFPA 13 & NFPA 72 as regulated by the North Ada County Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final6/20/20146/23/20146/23/2014APASS
DetailsJim Sly
Curt ###-####
1hr rated fire riser room OK and Engineering systems on structure, observed By Architect of record (Curt Barber) and approved as noted per letter dated June 18, 2014.
GCB-Courtesy6/16/20146/17/20146/17/2014ADONE
DetailsJim Sly
Curt ###-#### please call in advance to meet onsite
Talked to Curt. Want Architect of record to provide fix for non-continuous 1 hr ceiling at riser room, and OK to butt rock against insulation at ext. walls. Want Eng. of record to provide final letter of approval for entire steel structure and all Engineering systems.
GCB-Energy5/13/20145/13/20145/13/2014PPASS
DetailsDave Hannah
Curt ###-#### energy for 4-foot walls only
GCB-Framing5/8/20145/8/20145/9/2014PDONE
DetailsDave Hannah
Curt ###-#### late afternoon please call before
GCB-Framing5/8/20145/8/20145/8/2014PPASS
DetailsMike Jordan
Interior steel stud framed walls ok.
GCB-Framing4/28/20144/29/20144/29/2014PPEND
DetailsMike Jordan
Curt ###-####. contractor covering walls, no rough in inspections completed. Called curt and left message. Noted to contractor to not one side walls until all rough in and framing inspections have been completred.
GCB-Stem wall12/27/201312/30/201312/30/2013APASS
DetailsDave Hannah
Sean ###-####
GCB-Shearwall12/16/201312/17/201312/17/2013ACANC
DetailsJim Sly
Shawn ###-####
GCB-Shearwall12/5/201312/5/201312/5/2013PPEND
DetailsJim Sly
Shawn ###-#### retaining walls, call first
Wanted to pour retaining walls at loading dock. Per cold weather concrete provisions.....I didn't allow them to pour because they were not willing to heat it fo three days.
GCB-Footing12/2/201312/2/201312/2/2013PPASS
DetailsTom Arcoraci
###-#### footings on retaining wall
GCB-Fndatn/slab ins/fld vent11/6/201311/6/201311/7/2013PPASS
DetailsJim Sly
Shawn ###-####
GCB-Footing10/28/201310/28/201310/28/2013PPASS
DetailsJim Storey
###-####