Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberGCB14-00009
StatusFinaled
Name Flynner Homes
Site Address 3748 N WILLOWBAR
Project NameBLD2014-00009
Customer Number 
ePlanReviewNo
Description
To construct a new 3,126 square foot, three story (482 square foot 1st story / 1,412 square foot 2nd story / 1,232 square foot 3rd story), five bedroom, four bathroom, single family dwelling with a 1,191 square foot attached garage, and uncovered balconies. All work per the approved plans, attached plan review report, engineering, and all other reviewing agencies approvals. 1-hour fire-resistance construction is required on all projections closer than 3 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 3' from the property line are required to have 1-hour fire-resistance construction. FEMA (LOMR-F) noted on plans removing this property from the floodplain. Case No. 05-10-0330A **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final3/11/20153/12/20153/12/2015PPASS
DetailsDave Hannah
Dillon ###-####
GCB-Final3/10/20153/11/20153/12/2015PPEND
DetailsDave Hannah
Dillon ###-#### needs close risers to less than 4 inchs on front stairs and hand rail at bottom
GCB-Final11/5/201411/6/201411/6/2014ACANC
DetailsPhil Shearer
Dillon ###-####
GCB-Energy11/6/201411/6/201411/6/2014PPASS
DetailsPhil Shearer
Dillon ###-####
GCB-Framing11/6/201411/6/201411/6/2014PPASS
DetailsPhil Shearer
Dillon ###-####
GCB-Final11/5/201411/5/201411/5/2014ANR
DetailsDave Hannah
Dillon Schneider ###-#### - requested framing final and insulation inspection
GCB-Framing10/29/201410/30/201410/30/2014AFAIL
DetailsMike Jordan
Dillon ###-####. Complete all fireblocking, provide additional studs under 3rd. floor beam by stairs. Provide engineering for king studs at ground floor window opening picking up 2nd and 3rd. floor loads. ok to insulate.
GCB-Shearwall9/15/20149/16/20149/16/2014APART
DetailsJim Sly
Dylan ###-####
All Exterior shear nailing.......OK
GCB-Footing8/7/20148/8/20148/8/2014APASS
DetailsDave Hannah
Andy ###-#### requesting for around 10AM planter ftgs ok
GCB-Footing7/7/20147/8/20147/8/2014APASS
DetailsMike Jordan
Andy ###-####. Inspected aditional column pad footings that were missed. Also discused contractors plan on making sure that structural memembers will bear on footings once backfill has taken place.
GCB-Footing6/30/20147/1/20147/1/2014APART
DetailsDave Hannah
###-#### ext ftgsok but needs to dig out peir pads