GCB-Final | 1/28/2015 | 1/28/2015 | 1/28/2015 | P | PASS |
Dave Hannah
|
|
|
Curt ###-#### - call for access
|
GCB-Final | 12/12/2014 | 12/15/2014 | 12/16/2014 | P | FAIL |
Dave Hannah
|
|
|
Curt Barber. Final inspection reveled that changes had been made to the exterior elevations: additional doors and windows were added that wre not indicated on approved plans. The structure has upper story windows and no 2nd floor there is also no electrical, plumbing or mechanical installations and separate permits will be required. A correction notice was issued to supply new elevation drawings for review and approval.
|
GCB-Final | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PEND |
Dave Hannah
|
|
|
A final reinspection is required.
|
GCB-Final | 8/1/2014 | 8/1/2014 | 8/1/2014 | P | PASS |
Dave Hannah
|
|
|
Curt ###-####
|
GCB-Framing | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | PASS |
Jim Sly
|
|
|
Joe ###-#### late morning please
|
GCB-Footing | 6/19/2014 | 6/20/2014 | 6/20/2014 | A | PASS |
Mike Jordan
|
|
|
curt ###-#### footing and setbacks call for location of plans
|