GCB-Final | 10/15/2014 | 10/16/2014 | 10/16/2014 | P | PASS |
Jim Sly
|
|
|
Jessee or Ron at ###-####
|
GCB-Final | 10/15/2014 | 10/15/2014 | 10/15/2014 | P | CANC |
Jim Sly
|
|
|
Jessie ###-#### or Ron ###-#### Contr. scheduled for the next day.
|
GCB-Energy | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Phil Shearer
|
|
|
please call prior to inspection
|
GCB-Framing | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | PASS |
Dave Hannah
|
|
|
Jesse ###-#### please call to meet on-site
|
GCB-Shearwall | 7/1/2014 | 7/2/2014 | 7/2/2014 | A | PASS |
Tony Young
|
|
|
Ron ###-####,, exterior ok
|
GCB-Shearwall | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | FAIL |
Dave Hannah
|
|
|
Ron ###-#### please call first; shearnail inspection request crew used stapels plans call for nails
|
GCB-Assembly | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PASS |
Mike Jordan
|
|
|
Jesse ###-#### nailing inspection requestedbase and face layers of 5/8 type x rock for 2hr. firewall, 1st. floor at existing building. Shearwall nailing for new walls at existing building, 1st. floor.
|
GCB-Footing | 5/2/2014 | 5/5/2014 | 5/5/2014 | A | PASS |
Mike Jordan
|
|
|
Jessie ###-####. Interior footings and exterior north footing line ok.
|