Permit Information
Permit NumberGCB14-00076
StatusFinaled
Name Dan McCown
Site Address 304 E 39TH ST
Project NameBLD2014-00076
Customer Number 
ePlanReviewNo
Description
*** 8/29/14 PLAN MODIFICATION TO INCLUDE AN ENGINEERED FLOOD HAZARD FOUNDATION DESIGN TO INCLUDE ENCLOSED AREA BELOW DESIGN FLOOD ELEVATION. EXTERIOR WALL FLOOD OPENINGS ARE PROVIDED.*** To pour 174 lineal foot of footings/foundation walls for relocation of a 1,414 sq. ft. from 2005 N. 20th Street per approved plans, attached plan review report, and all other reviewing agencies final approvals. The Building Official has determined carbon monoxide poisoning, smoke and fire related hazards to be specific hazards associated with buildings and/or structures without smoke and carbon monoxide detection and alarm systems that do not meet current building codes. Carbon monoxide poisoning, smoke and fire related hazards are substantial hazards because the likelihood of death and or injury from said hazards increases in buildings and/or structures. The existing portions of buildings or structures with non-existent or inadequate smoke and carbon monoxide detection and alarm systems that do not meet current building codes must be retrofitted to meet current code requirements. This lot is within a Floodplain area. An elevation certificate is required to be submitted and approved prior to calling for a framing inspection. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final1/25/20161/25/20161/25/2016PPASS
DetailsDave Hannah
Sean ###-####
GCB-Final1/4/20161/4/20161/5/2016PFAIL
DetailsDave Hannah
Shaun ###-#### needs co2 detector insulation and vis queen crawl flood plan cert address
GCB-Fndatn/slab ins/fld vent9/23/20149/24/20149/25/2014PPASS
DetailsDave Hannah
Anton ###-####
GCB-Footing9/22/20149/23/20149/23/2014PDEFR
DetailsMike Jordan
Anton ###-####. Contractor did not have approved plans on site. Noted to concrete subcontractor, that if he decides to place concrete, he is proceeding at his own risk. Approved plans must be on site for stemwall inspection.