FIRE-Final Inspection | 1/21/2015 | 1/22/2015 | 1/22/2015 | A | FAIL |
Troy Cobbley
|
|
|
Could not make contact with contractor on site. Could not find approved drawings. Left message on contractors phone. Call prior to going Phone #: 2088701943 >> Cou Kyle Cooper
|
GCB-Final | 1/20/2015 | 1/21/2015 | 1/21/2015 | A | PASS |
Dave Hannah
|
|
|
Kyle ###-####
|
GCB-Final | 1/16/2015 | 1/20/2015 | 1/20/2015 | A | PEND |
Dave Hannah
|
|
|
Kyle ###-#### needs to change door hardwear on restroom and break room
|
GCB-Framing | 12/31/2014 | 12/31/2014 | 12/31/2014 | P | PART |
Mike Jordan
|
|
|
Kyle ###-####. Per contractor, the architect has reclassified building as type 3 building. Will resubmit as plan mod for approval. Framing is ok.
|
GCB-Framing | 12/30/2014 | 12/30/2014 | 12/30/2014 | P | FAIL |
Mike Jordan
|
|
|
Kyle ###-#### - requested call ahead. Noted type 2B construction for building. Interior framing for breakroom and unisex restroom constructed from wood studs. Correction notice issued to have contractor replace framing with non combustible framing or have architect see if building can be reclassified as type VB or type 3. Correction notice issued.
|
GCB-Framing | 12/16/2014 | 12/17/2014 | 12/17/2014 | A | NR |
Dave Hannah
|
|
|
Kyle ###-####
|
GCB-Footing | 10/24/2014 | 10/27/2014 | 10/30/2014 | P | PEND |
Dave Hannah
|
|
|
Kyle ###-#### contractor requested 1PM needs spec inspection
|