GCP-Final | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | PASS |
Daryl Spivey
|
|
|
Patty ###-####
|
GCP-Final | 9/12/2014 | 9/15/2014 | 9/15/2014 | P | PART |
Bill VanDegrift
|
|
|
###-#### partial final temp occ pk
|
GCP-Final | 9/11/2014 | 9/12/2014 | 9/12/2014 | P | PART |
Daryl Spivey
|
|
|
Inseslman ###-#### kitchen walk thru..........not ready yet.........sinks need to be anchored........ds
|
GCP-Final | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### Partial final only all rooms except for 6 are complete.........public restrooms, finish rooms left and kitchen are left to finish.......ds
|
GCP- Rough-in | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Bill VanDegrift
|
|
|
Wes ###-#### ri ok
|
GCP- Rough-in | 7/15/2014 | 7/15/2014 | 7/16/2014 | P | PASS |
Bill VanDegrift
|
|
|
Wes ###-#### ri ok
|
GCP- Rough-in | 7/2/2014 | 7/3/2014 | 7/3/2014 | A | PART |
Daryl Spivey
|
|
|
kitchen area
|
GCP- Rough-in | 6/24/2014 | 6/25/2014 | 6/25/2014 | A | PART |
Jim Johnson
|
|
|
Inselman ###-#### test on D W V and one roof and overflow drain marked on plan,s test ok
|
GCP- Rough-in | 6/20/2014 | 6/23/2014 | 6/23/2014 | A | PART |
Daryl Spivey
|
|
|
patty ###-#### as marked on plan........ds
|
GCP- Rough-in | 6/19/2014 | 6/20/2014 | 6/20/2014 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### as marked on plan............ds
|
GCP- Rough-in | 6/11/2014 | 6/12/2014 | 6/12/2014 | A | PART |
Daryl Spivey
|
|
|
Inselman ###-#### W/V tested ok as marked.........ds
|
GCP- Rough-in | 6/10/2014 | 6/11/2014 | 6/11/2014 | A | PART |
Daryl Spivey
|
|
|
Inselman ###-#### waste and vent tested ok as marked on plan................ds
|
GCP- Rough-in | 6/4/2014 | 6/5/2014 | 6/5/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### water tested in area marked on plan.......ds
|
GCP- Rough-in | 5/28/2014 | 5/29/2014 | 5/29/2014 | A | PART |
Jim Johnson
|
|
|
###-#### D W V and water marked on plan test ok
|
GCP- Rough-in | 5/14/2014 | 5/15/2014 | 5/15/2014 | A | PART |
Daryl Spivey
|
|
|
Inselman ###-#### waste and vent tested ok as marked on plans............ds
|
GCP- Rough-in | 5/13/2014 | 5/14/2014 | 5/14/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### waste and vent tested ok as marked on plan........ds
|
GCP- Rough-in | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### waste and vent as marked on plan.........ds
|
GCP- Rough-in | 5/9/2014 | 5/12/2014 | 5/12/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### waste and vent tested ok as marked on plan...........ds
|
GCP- Rough-in | 5/8/2014 | 5/9/2014 | 5/9/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### waste and vent in areas marked on plan........ds
|
GCP- Rough-in | 5/8/2014 | 5/8/2014 | 5/8/2014 | P | PART |
Daryl Spivey
|
|
|
467.4416 waste and vent tested ok as marked on prints........ds
|
GCP- Rough-in | 5/6/2014 | 5/7/2014 | 5/7/2014 | P | PART |
Daryl Spivey
|
|
|
Inselman Plumbing ###-#### as marked on plans waste and vent only....ds
|
GCP- Rough-in | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PART |
Bill VanDegrift
|
|
|
Inselman Plumbing ###-#### dwv 133 through 139 test ok
|
GCP- Rough-in | 5/2/2014 | 5/5/2014 | 5/5/2014 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### as marked on plan tested ok.......ds
|
GCP- Rough-in | 4/30/2014 | 5/1/2014 | 5/1/2014 | A | PART |
Daryl Spivey
|
|
|
Patty 467.4416 west side of east end hallway tested ok.......ds
|
GCP- Rough-in | 4/29/2014 | 4/30/2014 | 4/30/2014 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### Grace Assisited Living east side of east wing wasdte vent and water tested ok............ds
|
GCP-Under Floor | 3/28/2014 | 3/31/2014 | 3/31/2014 | P | PASS |
Daryl Spivey
|
|
|
patty ###-#### groundwork G/W complete............kitchen area tested ok................ds
|
GCP-Under Floor | 3/25/2014 | 3/26/2014 | 3/26/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### groundwork inspection all rooms groundwork done.......kitchen area is left to do............ds
|
GCP-Under Floor | 3/18/2014 | 3/19/2014 | 3/19/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-####ground work mid west side ok...........ds
|
GCP- Rough-in | 3/17/2014 | 3/18/2014 | 3/18/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### groundwork inspection northwest end tested ok.........ds
|
GCP-Under Floor | 3/14/2014 | 3/17/2014 | 3/17/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### s/w trunk line and south end plumbing tested.........ds
|
GCP-Under Floor | 3/13/2014 | 3/14/2014 | 3/14/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### groundwork G/W done in middle section...........ds
|
GCP-Under Floor | 3/10/2014 | 3/11/2014 | 3/11/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### groundwork S/W trunk lines tested ok.....ds
|
GCP-Under Floor | 3/10/2014 | 3/10/2014 | 3/10/2014 | P | NR |
Daryl Spivey
|
|
|
Wes got rained out...........ds
|
GCP- Rough-in | 3/7/2014 | 3/10/2014 | 3/10/2014 | A | NR |
Daryl Spivey
|
|
|
Patty ###-####
|
GCP- Rough-in | 3/6/2014 | 3/7/2014 | 3/7/2014 | A | PART |
Bill VanDegrift
|
|
|
Grnkwork, Patty ###-#### small section entering south west corner ok
|
GCP-Under Floor | 3/6/2014 | 3/6/2014 | 3/6/2014 | P | PART |
Daryl Spivey
|
|
|
wes west-sw area tested ok.........ds
|
GCP- Rough-in | 3/4/2014 | 3/5/2014 | 3/5/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### Inselman Plumbing n/w section...mech rm and salon gw tested ok.........ds
|
GCP- Rough-in | 2/28/2014 | 3/3/2014 | 3/3/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### g/w on north west end tested ok.......ds
|
GCP- Rough-in | 2/19/2014 | 2/20/2014 | 2/20/2014 | P | PART |
Daryl Spivey
|
|
|
###-#### ground work on 2nd line from east all tested ok...............ds
|
GCP- Rough-in | 2/18/2014 | 2/19/2014 | 2/19/2014 | P | PART |
Daryl Spivey
|
|
|
Patty ###-#### partial G/W tested ok.............ds
|
GCP- Rough-in | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PART |
Daryl Spivey
|
|
|
###-#### south east g/w tested ok.........ds
|
GCP- Rough-in | 2/13/2014 | 2/14/2014 | 2/14/2014 | P | CANC |
Daryl Spivey
|
|
|
###-#### Inspection cancelled from web by: Barbara Stitt
|
GCP-Site system | 2/4/2014 | 2/5/2014 | 2/5/2014 | P | PART |
Daryl Spivey
|
|
|
Patty Inselman plumbing ###-#### groundwork inspection request 2nd gridline from east...north end groundwork tested ok...........ds
|
GCP-Site system | 1/31/2014 | 2/3/2014 | 2/3/2014 | A | PART |
Daryl Spivey
|
|
|
Lane ###-#### partial on south end of second gridline from east side...........tested ok.........ds
|
GCP-Site system | 1/30/2014 | 1/31/2014 | 1/31/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### ground work for 2 showers and 2 w/c on north east tested ok...2nd trunk line from east tied in outside bld ok.............ds
|
GCP- Rough-in | 1/28/2014 | 1/29/2014 | 1/29/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### grease line into and out of tank and tie in to sanitary tested from just inside bld ok............ds
|
GCP- Rough-in | 1/22/2014 | 1/23/2014 | 1/23/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### east end G/W tested ok.........ds
|
GCP-Under Floor | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | PART |
Daryl Spivey
|
|
|
###-#### east side g/w testedto column j.........ds
|
GCP-Under Floor | 1/17/2014 | 1/21/2014 | 1/21/2014 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### groundwork inspection northeast corner tested ok........ds
|
GCP-Site system | 1/16/2014 | 1/17/2014 | 1/17/2014 | P | PART |
Daryl Spivey
|
|
|
###-#### se corner tested ok......ds
|
GCP-Site system | 11/26/2013 | 11/27/2013 | 11/27/2013 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### outside line that ties 2 west side trunk lines together tested ok..........ds
|
GCP- Rough-in | 11/21/2013 | 11/22/2013 | 11/22/2013 | A | CANC |
Daryl Spivey
|
|
|
Patty ###-#### groundwork
|
GCP-Under Floor | 11/22/2013 | 11/22/2013 | 11/22/2013 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### groundwork north outside lateral connecting 2 east side main drains............tested ok..........ds
|
GCP- Rough-in | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | CANC |
Daryl Spivey
|
|
|
Lane ###-####
|
GCP-Under Floor | 11/19/2013 | 11/19/2013 | 11/19/2013 | A | PART |
Daryl Spivey
|
|
|
Lane ###-#### 4th trunkline sewer main from east side tested ok...........ds
|
GCP- Rough-in | 11/15/2013 | 11/18/2013 | 11/18/2013 | A | CANC |
Daryl Spivey
|
|
|
Patty ###-####
|
GCP-Under Floor | 11/18/2013 | 11/18/2013 | 11/18/2013 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### 3rd main in from east side tested ok........ds
|
GCP- Rough-in | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | CANC |
Daryl Spivey
|
|
|
Patty ###-####
|
GCP-Under Floor | 11/15/2013 | 11/15/2013 | 11/15/2013 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### main trunk line for waste 2nd line from east tested ok.......ds
|
GCP- Rough-in | 11/13/2013 | 11/14/2013 | 11/14/2013 | A | PART |
Daryl Spivey
|
|
|
Patty ###-#### partial underground......east end main building drain tested ok..............ds
|