GRD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | A | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 12/18/2017 | 12/18/2017 | 12/18/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per Scott Arellano since the plans have been misplaced the fire dept access and the two fire hydrants could be verified from the civil sheets of the project approved building permit plans.
|
FIRE-Final Inspection | 12/17/2017 | 12/18/2017 | 12/18/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per Scott Arellano since the plans have been misplaced the fire dept access and the two fire hydrants could be verified from the civil sheets of the project approved building permit plans.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents. No inspection was performed
Phone #: ###-#### Inspection requested via web by David Scaggs
|