Final | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Chad Schwendiman
|
|
|
|
Final | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | PART |
Chad Schwendiman
|
|
|
Bj 5730755 Inspection requested via web by william kerwin - temporary occupancy okay, Still need to complete the condensate in units 309, 319, 223
|
Final | 8/31/2016 | 8/31/2016 | 8/31/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Bj 5730755 Inspection requested via web by william kerwin - still need to remove fire caulk from dampers in mechanical rooms per previous discussions
|
Final | 8/30/2016 | 8/30/2016 | 8/30/2016 | P | PART |
Chad Schwendiman
|
|
|
bj###-#### Inspection requested via web by william kerwin - all units okay except for 110, 113, 212, 223, 225, 227, 303, 309, 311, 319, 324
|
Final | 8/26/2016 | 8/26/2016 | 8/26/2016 | P | FAIL |
Chad Schwendiman
|
|
|
Call montessori on the trim please 9724667 Inspection requested via web by william kerwin - Need clamps on condensate tubing under sinks, need fire damper installed on fresh air duct to the corridoor mechanical rooms, need to finish ducting to corridoor units, need permanent ladder to access equipment on the roof
|
Conference | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | DONE |
Chad Schwendiman
|
|
|
Phone ###-####
|
Conference | 7/21/2016 | 7/21/2016 | 7/21/2016 | A | DONE |
Chad Schwendiman
|
|
|
Phone ###-####
|
Conference | 4/25/2016 | 4/25/2016 | 4/25/2016 | A | DONE |
Chad Schwendiman
|
|
|
Bj ###-#### - went over the approved drawings with Bj to address the condensate piping and exhaust fan location and duct work. They need to install per the approved drawing or provide documentation from the engineer showing that he approves of the changes
|
Rough-in | 4/22/2016 | 4/22/2016 | 4/22/2016 | A | PART |
Chad Schwendiman
|
|
|
Dropped ceilings. Bj 5730755. Thank You Inspection requested via web by william kerwin - okay to cover bathroom ceilings
|
Rough-in | 4/20/2016 | 4/20/2016 | 4/20/2016 | P | FAIL |
Chad Schwendiman
|
|
|
Bj 5730755. Dropped ceiling inspection Inspection requested via web by william kerwin - Need to remove combustable material from with in the return air plenum
|
Rough-in | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | NR |
Chad Schwendiman
|
|
|
BJ ###-#### Inspection requested via web by william kerwin
|
Rough-in | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | NR |
Chad Schwendiman
|
|
|
Ductwork in drop ceilings. Late afternoon Inspection requested via web by william kerwin
|
Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PART |
Chad Schwendiman
|
|
|
Firedamper inspection Inspection requested via web by william kerwin - fire damper retaining angles okay on 1st, and 2nd floor
|
Rough-in | 4/8/2016 | 4/8/2016 | 4/8/2016 | P | PART |
Chad Schwendiman
|
|
|
Phone ###-#### - retaining angle on supply plenum fire dampers okay in rooms 303, 306, 313, 315
|
Rough-in | 4/8/2016 | 4/8/2016 | 4/8/2016 | A | PART |
Chad Schwendiman
|
|
|
Late am. Firedamper inspection Inspection requested via web by william kerwin - retaining angles on fire dampers in supply plenums okay on the 3rd floor except for rooms 303, 306, 313,315
|
Rough-in | 3/30/2016 | 3/30/2016 | 3/30/2016 | P | PART |
Chad Schwendiman
|
|
|
firedamper reinspect. THANKS CHAD! Appreciate your professionalism! Inspection requested via web by william kerwin - okay to cover bottom of tgi's and trusses in the bathrooms
|
Conference | 3/30/2016 | 3/30/2016 | 3/30/2016 | A | PASS |
Ben Livingston
|
|
|
Meet on site
|
Rough-in | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | FAIL |
Chad Schwendiman
|
|
|
firedamper inspection. Inspection requested via web by william kerwin - need to square up the plenum boxs and fire dampersnin some of the rooms
|
Conference | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | DONE |
Chad Schwendiman
|
|
|
Rob ###-#### meet to go over fire dampers - nmet to go over the fire damper installation in the supply plenums
|
Conference | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | CANC |
Chad Schwendiman
|
|
|
Rob ###-#### - rescheduled for tomorrow morning
|
Rough-in | 2/25/2016 | 2/25/2016 | 2/25/2016 | A | PART |
Chad Schwendiman
|
|
|
Call Rob Inspection requested via web by william kerwin - Okay to cover the dwelling units ceiling and walls on all three floors except for the bathroom ceilings on the 1st and 2nd floor where the supply plenum box is located. Okay to cover 3rd floor corridoors
|
Conference | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | DONE |
Chad Schwendiman
|
|
|
Inspection requested via web by william kerwin - I recevied the listings for the southwark dampers at the grill locations. The greenheck dampers are not listed for the application on the supply plenums. Need to install a damper that is listed for the application
|
Conference | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | DONE |
Chad Schwendiman
|
|
|
Monte 9724667 Inspection requested via web by william kerwin - Need installation instructions for fire dampers to be able to approve.
|
Rough-in | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | CANC |
Chad Schwendiman
|
|
|
Rob ###-####
|