Final | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PASS |
Jack Reynolds
|
|
|
questions, please call Zac ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt - received email from engineer on louver AFF ok - also received email on operation of equipment - final ok -couldnt find card to sign onsite
|
Card not on site to sign | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | PASS |
Jack Reynolds
|
|
|
questions, please call Zac ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
|
Final | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | FAIL |
Jack Reynolds
|
|
|
ANY QUESTIONS, PLEASE CALL ZAC ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
- side wall exhaust and make up needs to be 12' AFF like the print shows. - Exhaust and make up air needs to be functional and it looks like the electrical contractor is working on this
|
Final | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | NR |
Jack Reynolds
|
|
|
questions you can call Zac Barnes ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt - unit heaters ok - need to see exhaust and make up air finished before final - need to add description on permit the work being done on exhaust and make up air outside the paint booth - talked with Kay from ultimate steel and paint booth is being done by another contractor. I told kay that the paint booth exhaust and makeup air ducting needs to have a mechanical permit pulled
|
Final | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | CANC |
Jack Reynolds
|
|
|
INSTALLER BRANDAN ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
|
Rough-in | 2/20/2019 | 2/20/2019 | 2/20/2019 | P | PART |
Jack Reynolds
|
|
|
INSTALLER BRANDAN ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt - unit heater flues need seams sealed per manufactures specs - also need to check with engineer about unit heater to the north and its termination point out the buidling being moved to the east wall. Prints show the termination point on the north wall - gas line is a high pressure system and each unit heater needs its regs and sediment traps/pressure ports installed. other contractor performed gas line for new building
|