Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberMEC19-02160
StatusFinaled
Name ASPEN HEATING AND AIR COND
Site Address 7039 W ROSEWOOD DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Addition: Mini split
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final9/19/20199/19/20199/19/2019PPASS
DetailsBrian Scoles
Phone #: ###-#### Inspection requested via web by Aaron Toomey- final ok
Rough-in6/25/20196/25/20196/25/2019PPASS
DetailsBrian Scoles
Phone #: ###-#### Inspection requested via web by Aaron Toomey- R/I ok
Pressure Test6/25/20196/25/20196/25/2019PPASS
DetailsBrian Scoles
Phone #: ###-#### Inspection requested via web by Aaron Toomey- 5lb flue pass- 20lb gas already passed
Rough-in6/24/20196/24/20196/24/2019PFAIL
DetailsJack Reynolds
Phone #: ###-#### Inspection requested via web by Aaron Toomey
- CSST gas line needs approved manufactures nail plates installed
- tankless water heater vent needs to be approved materials
- need to see a 5lb flue pressure test
Pressure Test6/24/20196/24/20196/24/2019PPASS
DetailsJack Reynolds
Phone #: ###-#### Inspection requested via web by Aaron Toomey
- 20lb gas pressure test ok
Rough-in6/23/20196/24/20196/24/2019AFAIL
DetailsJack Reynolds
Key is in light power box at back door Phone #: ###-#### Inspection requested via web by Aaron Toomey
- need stamped man J onsite
- 5lb flue pressure test fail gauge was at zero and PVC installed for vent needs to be solid core
- several locations need nail plates installed for line sets
- gas line needs 10 mill tape installed at penentration
- range vent needs backdraft damper
- 2nd systems looks like it needs finished
-line set in crawl needs supported
Pressure Test6/23/20196/24/20196/24/2019AFAIL
DetailsJack Reynolds
Key is in light power box at back door Phone #: ###-#### Inspection requested via web by Aaron Toomey
- 5lb flue pressure test fail gauge was at zero
- tankless water heater vent needs to be ran in solid core PVC
- re test 20lb gas after 10 mill tape is installed at penentration