Final | 3/16/2020 | 3/16/2020 | 3/16/2020 | P | PASS |
Jack Reynolds
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you!! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - final ok - occ card signed
|
Final | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | CANC |
Jack Reynolds
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - check R/I inspection from the afternoon of 3-11-20 for correction notice
|
Rough-in | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | FAIL |
Jack Reynolds
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - should have been a final not a R/I - A/C's need locking caps installed on service ports - line set penetrations need sealed and line set insulation needs UV protections - all fire damper access doors need installed and all dampers need labeled - commerical dryers need 2" min clearances to combustibles and insulation sheild installed in wall - dryers vent length is too long on both dryers - damper interlock with dryers needs adjusted
|
Rough-in | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | PASS |
Jack Reynolds
|
|
|
1st floor Men''s and Women''s restrooms. Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 2 bathrooms 1st floor R/I ok
|
Rough-in | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | FAIL |
Jack Reynolds
|
|
|
Rough-in on men''s and women''s bathroom, final on 2nd, 3rd, and 4th floor if possible. Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - plan mod is under review
|
Rough-in | 1/28/2020 | 1/30/2020 | 1/30/2020 | A | PASS |
Brian Scoles
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum- lobby and hallway ok- 2 fire damper angles ok- access on duct and ceiling ok- duct insulation installed 2 locations- ok for cover
|
Rough-in | 1/27/2020 | 1/28/2020 | 1/28/2020 | P | FAIL |
Jack Reynolds
|
|
|
Rough in for first floor lobby and hallways, please call Bryan at least 30 in prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - hard lid cover in lobby and hallway 1st floor fail - fire dampers missing retaining angles - fire damper in duct access door needs moved for access from ceiling - two locations of duct insulation need installed
|
Conference | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PASS |
Jack Reynolds
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum
|
Rough-in | 1/8/2020 | 1/8/2020 | 1/8/2020 | A | PART |
Jack Reynolds
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum 2- 8" F/S damper clearances ok all bathroom hard lids ok for cover other than two guest bathrooms in the corridor next to gym. - talked with HVAC contractor and general about fire dampers in ceiling/floor assembly per approved drawnings. Contractor says they will not be able to fit a fire damper in ceiling space. Explained that they will need to have this issue looked at by design professional and then reviewed by city before moving foward.
|
Rough-in | 12/20/2019 | 12/23/2019 | 12/23/2019 | A | FAIL |
Jack Reynolds
|
|
|
Please call Bryan at least 30 min prior to inspection, thank you, Merry Christmas! Phone #: ###-#### Inspection requested via web by Rhonda Marcum
- duct seal ok for insulation - two 8" F/S dampers need proper clearances - two exhaust fans penetrating ceiling/floor assembly need dampers and access doors installed - two exhaust flues for commerical dryers not installed yet
|
Rough-in | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PART |
Jack Reynolds
|
|
|
2nd, 3rd,; 4th floor exhaust rough in. Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - 2nd/3rd/4th floor exhaust ducting R/I ok
|
Rough-in | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | FAIL |
Jack Reynolds
|
|
|
2nd ; 3rd floor exhaust fans, 4th floor radiant dampers. Please call Bryan at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - exhaust fans are not installed per prints on 2nd, 3rd and 4th floor
|
Rough-in | 7/30/2019 | 8/1/2019 | 8/1/2019 | A | PASS |
Jack Reynolds
|
|
|