Final | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PASS |
Brian Scoles
|
|
|
Please call Pat prior to arrival at ###-####. Phone #: ###-#### Inspection requested via web by Maira Napoles- final ok- will sign card on other mech contractor inspection
|
Rough-in | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Brian Scoles
|
|
|
Please call Pat prior to arrival at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Maira Napoles
|
Pressure Test | 12/17/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Brian Scoles
|
|
|
Please call Pat prior to arrival at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Maira Napoles- 60lb gas pass whole system
|
Rough-in | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Brian Scoles
|
|
|
Please call Pat prior to arrival at ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Maira Napoles- 60lb gas pass tagged meter location- still need to see lower pressure tests- need inert tape on exterior pentration by meter and concrete remove around pipe by final
|