Permit Information
Permit NumberMEC19-03841
StatusFinaled
Name IDAHO AIR INNOVATIONS LLC
Site Address 7009 W FRANKLIN RD
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration: Installing 2 class 1 grease exhaust hoods, grease duct, makeup air and fire wrap.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final10/9/201910/9/201910/9/2019PPASS
DetailsTroy James
Plans are on site, equipment is set and fire system is getting its final this afternoon. Phone #: ###-#### Inspection requested via web by Drew Tverdy
Final10/8/201910/8/201910/8/2019APART
DetailsBrian Scoles
Emailing balance report to Brian. Phone #: ###-#### Inspection requested via web by Drew Tverdy- all equipment needs set into working order under class 1 hood and maintain 6" clearance on all sides of appliance and all moveable appliances tethered- need to install SS panel north end of hood- air balance report ok- still need approved plan mod drawings onsite to review them
Rough-in9/29/20199/30/20199/30/2019APASS
DetailsBrian Scoles
Rough in before last piece of hood shroud goes on. Phone #: ###-#### Inspection requested via web by Drew Tverdy- MAU duct and seal above hood ok- ok for ss skirting panels to be installed above hood
Rough-in9/22/20199/23/20199/23/2019APASS
DetailsBrian Scoles
Light test on hood to duct connection for final cover. Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test at 2 locations to hoods ok- MAU intake needs plumbing vents/ water heater vent extended up 3 feet above inlet or 10 feet away- exhaust fans on roof ok
Rough-in9/18/20199/18/20199/18/2019PPASS
DetailsBrian Scoles
Light test in grease duct. Will be ready by 12:30 Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test pass 2 drops- will look at final 4 welds when installed to hood and curb