INSP-Final | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | FAIL |
Troy Cobbley
|
|
|
Hydro Underground failded due to visible leak at guage
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2015 | 5/5/2015 | 5/5/2015 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in.
|
INSP-Supply line flush | 4/6/2015 | 4/7/2015 | 4/8/2015 | A | PASS |
Tim Frost
|
|
|
Passed flush
|
INSP-Sprinkler Rough-in/Hydro | 1/12/2015 | 1/13/2015 | 1/13/2015 | A | PASS |
Troy Cobbley
|
|
|
Remaining underground piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2015 | 1/9/2015 | 1/9/2015 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping up to the bottom of the DI is ok to bury.
|
INSP-Sprinkler Rough-in | 1/8/2015 | 1/9/2015 | 1/8/2015 | A | PASS |
Troy Cobbley
|
|
|
Piping from the hot tap to 20'-0" ok for cover. Additional fittings have been installed that will need to be accounted for in the hydraulic calculations.
|
INSP-Sprinkler Rough-in | 1/7/2015 | 1/7/2015 | 1/7/2015 | P | FAIL |
Troy Cobbley
|
|
|
Piping that had been previously buried has been removed. No new piping has been installed yet due to contractor (not applicant) waiting for a "road box" to continue installation. Tribal Fire was going to stop at project site and verify installation.
|
INSP-Sprinkler Rough-in | 12/22/2014 | 12/23/2014 | 12/23/2014 | A | FAIL |
Troy Cobbley
|
|
|
Inspection turned into conference since the piping installed in the trench does not meet the minimum 4'6" bury requirement. Piping needs to be installed at the correct depth and inspected for approval to cover which will include thrust blocks.
|