INSP-Final | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed again due to loss of pressure
|
INSP-Sprinkler Rough-in/Hydro | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to visible loss of pressure at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2016 | 5/18/2016 | 5/18/2016 | P | FAIL |
Troy Cobbley
|
|
|
Test failed due to a split valve. Rescheduled for tomorrow
|
INSP-Conference | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | DONE |
Katie Marron
|
|
|
Discussed requirements for occupancy with Mike (superintendent).
|
INSP-Sprinkler Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PEND |
Katie Marron
|
|
|
Rough-in inspection completed. Verified all uprights and pendant drops. One hangar missing see plans on site. Hangar will be visible at final from drop ceiling. OK to cover PENDING resubmitted calcs for remote area 2 due to two sprinkler heads added to the calc area.
|
INSP-Sprinkler Rough-in | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled, point of contact on job could not get a set of approved resubmittal blue prints to have for inspection. Contractor will reschedule inspection for later date.
|
INSP-Sprinkler Rough-in | 3/21/2016 | 3/22/2016 | 3/22/2016 | P | FAIL |
Troy Cobbley
|
|
|
Plan modifications needed due to extensive changes needed such as adding upright sprinkler coverage that is missing is some locations and additional fittings have been added in the mains and riser nipples.
|